8321 N STEPHEN LANE 91304
Certificate Information: 8321 N STEPHEN LANE 91304
- Application / Permit
- 22010-20000-03565
- Plan Check / Job No.
- B22VN11162
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22' X 30' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH 15' X 30' PATIO ATTACHED
- Permit Issued
- Issued on 2/27/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | SELLA BENYAMIN |
| Corrections Issued | 8/8/2022 | SELLA BENYAMIN |
| Quality Review Completed | 8/10/2022 | STEVEN KIM |
| Building Plans Picked Up | 8/10/2022 | APPLICANT |
| Plan Check Approved | 2/24/2023 | SELLA BENYAMIN |
| Issued | 2/27/2023 | APPLICANT |
| CofO in Progress | 3/27/2026 | CHRIS CHRISTENSEN |
| Permit Finaled | 4/17/2026 | JOHN JANSON |
| CofO Issued | 4/17/2026 | JOHN JANSON |
| Permit Finaled | 4/17/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/11/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/11/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/11/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/11/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/11/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 2/8/2023 | NADER ISKANDER |
| Low Impact Development | Cleared | 2/8/2023 | LUIS LUVANO |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 2/10/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/10/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Cali Energy; Lic. No.: 1032379-B | 19145 PARTHENIA ST STE E NORTHRIDGE, CA 91324 |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/24/2023 | No Access for Inspection | KRISTEN CAUSEY |
| Sewer | 3/24/2023 | No Access for Inspection | KRISTEN CAUSEY |
| Underground Mechanical | 3/24/2023 | No Access for Inspection | KRISTEN CAUSEY |
| Sewer | 3/28/2023 | Approved | KRISTEN CAUSEY |
| Excavation/Setback/Form/Re-Bar | 4/5/2023 | Approved | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 4/5/2023 | Approved | KRISTEN CAUSEY |
| Underground Mechanical | 4/5/2023 | Partial Approval | KRISTEN CAUSEY |
| Excavation/Setback/Form/Re-Bar | 4/11/2023 | Partial Inspection | KRISTEN CAUSEY |
| Underground Mechanical | 4/11/2023 | Partial Approval | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2023 | Partial Approval | KRISTEN CAUSEY |
| Wood Frame | 4/21/2023 | Partial Inspection | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Wood Frame | 5/1/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/21/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 7/21/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 7/21/2023 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 7/21/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 7/21/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 7/21/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/20/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 9/20/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 9/20/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 9/20/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 9/20/2023 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 9/20/2023 | Partial Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 9/20/2023 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/25/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/25/2023 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 10/25/2023 | Approved | CHRIS CHRISTENSEN |
| Insulation | 10/25/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/25/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 10/25/2023 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 10/25/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 10/25/2023 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 11/3/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 11/3/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Shower Pan | 11/3/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 12/4/2023 | Approved | JEFFREY HARTLINE |
| Shower Pan | 12/4/2023 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 12/5/2023 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 12/5/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 2/12/2026 | Approved | CHRIS CHRISTENSEN |
| Final | 2/12/2026 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 2/12/2026 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 2/12/2026 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 2/12/2026 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/12/2026 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 2/12/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 2/12/2026 | Approved | CHRIS CHRISTENSEN |
| Final | 2/25/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Gas Test | 2/25/2026 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 2/25/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 3/26/2026 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Service/Power Release | 3/26/2026 | Approved | CHRIS CHRISTENSEN |