6055 N CRANER AVE 1-2 91606

Certificate Information: 6055 N CRANER AVE 1-2 91606

Application / Permit
21010-10000-04389
Plan Check / Job No.
B21LA15957
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3-STORY FRONT DUPLEX WITH RECREATION ROOM
Permit Issued
Issued on 6/17/2022
Issuing Office
Current Status
CofO Issued on 8/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 DANIEL YIP
Corrections Issued 10/7/2021 DANIEL YIP
Quality Review Completed 10/8/2021 ALLEN MANALANSAN
Building Plans Picked Up 10/20/2021 APPLICANT
Applicant returned to address corrections 12/22/2021 DANIEL YIP
Applicant returned to address corrections 5/10/2022 DANIEL YIP
Plan Check Approved 6/9/2022 DANIEL YIP
Issued 6/17/2022 APPLICANT
CofO in Progress 8/15/2023 JOHN HAYES
Permit Finaled 8/25/2023 RUBEN SALAS
CofO Issued 8/25/2023 RUBEN SALAS
Permit Finaled 8/25/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/13/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 10/13/2021 DAGOVERTO GUERRERO
Permit Cleared 10/13/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 10/13/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 1/4/2022 GILBERT URREA
Frnt yard landscape/Water mgmt Cleared 1/5/2022 ERIKA BARBERO
Opn space landscape/Water mgmt Cleared 1/5/2022 ERIKA BARBERO
Miscellaneous Cleared 1/6/2022 ERIKA BARBERO
Low Impact Development Cleared 4/15/2022 TA ANH
Roof/Waste drainage to street Cleared 4/21/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Xiao,, Qiang; Lic. No.: S5289 1520 BROOKHOLLOW #45      SANTA ANA, CA 92705

Inspector Information

JOSE AVILA, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/17/2022 Partial Approval JOHN HAYES
Underground Mechanical 8/17/2022 Not Ready for Inspection JOHN HAYES
Underground Mechanical 8/18/2022 Approved JOHN HAYES
Footing/Foundation/Slab 9/7/2022 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 9/14/2022 Approved ALAN MORELOS
Special/Order Compliance 9/16/2022 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/28/2022 Partial Approval ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 10/6/2022 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Partial Approval JOHN HAYES
HVAC-Rough 11/18/2022 Corrections Issued CALEB MEISTER
ELECTRICAL-Rough 12/14/2022 Approved JOHN HAYES
HVAC-Rough 12/14/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 12/20/2022 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Partial Approval JOHN HAYES
Gas Test 12/20/2022 Partial Approval JOHN HAYES
HVAC-Rough 12/20/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 12/20/2022 Approved JOHN HAYES
Shower Pan 12/20/2022 Approved JOHN HAYES
BUILDING-Rough-Frame 12/27/2022 Approved JOHN HAYES
Green Building Rough 12/27/2022 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 12/27/2022 Approved JOHN HAYES
Verify Sprinkler Sign Off 12/27/2022 Approved JOHN HAYES
Insulation 1/3/2023 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 1/3/2023 Partial Approval JOHN HAYES
Insulation 1/5/2023 Approved JOHN HAYES
Drywall Nailing 1/17/2023 Approved JOHN HAYES
Interior/Exterior Lathing 1/17/2023 Approved JOHN HAYES
Special/Order Compliance 5/24/2023 Not Ready for Inspection JOHN HAYES
Underground Mechanical 5/24/2023 Corrections Issued JOHN HAYES
Special/Order Compliance 5/31/2023 Off-Hour Fees Due
Underground Mechanical 5/31/2023 Off-Hour Fees Due
Special/Order Compliance 6/2/2023 Approved JOHN HAYES
Underground Mechanical 6/2/2023 Approved JOHN HAYES
ELECTRICAL-Final 7/26/2023 Partial Approval DAVID MATSON
Final 7/26/2023 Corrections Issued DAVID MATSON
Footing/Foundation/Slab 7/26/2023 Approved DAVID MATSON
Green Building Final 7/26/2023 Approved DAVID MATSON
HVAC-Final 7/26/2023 Approved DAVID MATSON
PLUMBING-Final 7/26/2023 Approved DAVID MATSON
SGSOV-Seismic Gas S/O Valve 7/26/2023 SGSOV Not Ready DAVID MATSON
Service/Power Release 7/26/2023 Not Ready for Inspection DAVID MATSON
Smoke Detectors 7/26/2023 Approved DAVID MATSON
ELECTRICAL-Final 8/8/2023 Not Ready for Inspection JOHN HAYES
Final 8/8/2023 Corrections Issued JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/8/2023 SGSOV Not Ready JOHN HAYES
Service/Power Release 8/8/2023 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 8/14/2023 Approved JOHN HAYES
Final 8/14/2023 OK to Issue CofO JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/14/2023 SGSOV Approved JOHN HAYES
Service/Power Release 8/14/2023 Approved JOHN HAYES