5900 S WESTERN AVE 90047
Certificate Information: 5900 S WESTERN AVE 90047
- Application / Permit
- 98010-10000-02353
- Plan Check / Job No.
- CC07953
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (6) Church
- Work Description
- NEW SANCTUARY/CHURCH.
- Permit Issued
- Issued on 5/28/1999
- Issuing Office
- Metro
- Current Status
- Issued on 5/28/1999
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Fees Due | 8/5/1998 | OSCAR DIAZ |
| Submitted | 8/5/1998 | ANITA TANG |
| PC Assigned | 8/20/1998 | KIRAN PATEL |
| No Progress | 8/28/1998 | KIRAN PATEL |
| PC Assigned | 9/4/1998 | WESLEY FARRELL |
| PC Assigned | 9/4/1998 | BRIAN KANEGAWA |
| PC Assigned | 9/16/1998 | BRIAN KANEGAWA |
| Issued | 5/28/1999 | MAUREEN O'CONNOR |
Permit Application Clearance Information
| Driveway approval | Cleared | 4/13/1999 | RAY LAU |
| Transportation Demand Ord. | Cleared | 4/13/1999 | RAY LAU |
| Building Permit Clearance | Cleared | 4/29/1999 | ROBERT REIMERS |
| Highway dedication | Cleared | 4/29/1999 | ANDY FLORES |
| DAS Clearance | Cleared | 4/30/1999 | WAI LAU |
| A-Permit | Cleared | 5/24/1999 | VALENTINO PUEBLOS |
| Parking Lot landscape | Cleared | 5/24/1999 | ALBERT LANDINI |
| Project located in CRA area | Cleared | 5/24/1999 | EDWARD HUANG |
| Sewer availability | Cleared | 5/24/1999 | VALENTINO PUEBLOS |
| ZA Case | Cleared | 5/24/1999 | ALBERT LANDINI |
| ZI | Cleared | 5/26/1999 | BRIAN KANEGAWA |
Contact Information
| Architect | Suarez, Hugo; Lic. No.: C10561 | 200 E DEL MAR BLVD #300 PASADENA, CA 91105 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Masonry Wall or Backfill | 6/24/1999 | Approved | JAMES BANGHAM |
| Excavation/Setback/Form/Re-Bar | 6/30/1999 | Not Ready for Inspection | JAMES BANGHAM |
| Excavation/Setback/Form/Re-Bar | 7/1/1999 | Not Ready for Inspection | JAMES BANGHAM |
| Floor/Roof Diaphgm/Shear Wall | 7/2/1999 | Not Ready for Inspection | JAMES BANGHAM |
| Excavation/Setback/Form/Re-Bar | 7/6/1999 | Corrections Issued | LEON THOMAS |
| Excavation/Setback/Form/Re-Bar | 7/7/1999 | Not Ready for Inspection | LEON THOMAS |
| Excavation/Setback/Form/Re-Bar | 7/8/1999 | Partial Approval | LEON THOMAS |
| Excavation/Setback/Form/Re-Bar | 7/28/1999 | Partial Approval | LEON THOMAS |
| Excavation/Setback/Form/Re-Bar | 8/19/1999 | Not Ready for Inspection | LEON THOMAS |
| Rough Frame | 9/2/1999 | Not Ready for Inspection | LEON THOMAS |
| Excavation/Setback/Form/Re-Bar | 9/3/1999 | Corrections Issued | LEON THOMAS |
| Excavation/Setback/Form/Re-Bar | 9/13/1999 | Approved | LEON THOMAS |
| Footing/Foundation/Slab | 2/29/2000 | Approved | LEON THOMAS |
| Rough-Frame | 2/29/2000 | Not Ready for Inspection | LEON THOMAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2001 | Not Ready for Inspection | LEON THOMAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2001 | Corrections Issued | LEON THOMAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2001 | Partial Approval | LEON THOMAS |
| Rough-Frame | 1/16/2003 | Partial Inspection | PAUL FRAUSTO |
| Rough-Frame | 1/21/2003 | Approved | PAUL FRAUSTO |
| Rough-Frame | 6/4/2003 | Partial Approval | PAUL FRAUSTO |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2003 | Approved | PAUL FRAUSTO |
| Interior/Exterior Lathing | 8/12/2004 | Corrections Issued | SAKO AGHAZARIAN |
| Interior/Exterior Lathing | 8/13/2004 | Approved | SAKO AGHAZARIAN |
| Drywall Nailing | 2/7/2007 | Corrections Issued | STEPHEN REED |
| Special/Order Compliance | 2/7/2007 | Corrections Issued | STEPHEN REED |
| Drywall Nailing | 3/7/2007 | Not Ready for Inspection | RICKEY JACKSON |
| Drywall Nailing | 3/21/2007 | Corrections Issued | RICKEY JACKSON |
| Drywall Nailing | 4/10/2007 | Not Ready for Inspection | WINFIELD HINKSON |
| Rough-Frame | 4/10/2007 | Partial Approval | WINFIELD HINKSON |
| Final | 3/4/2008 | Reroute RFI | WINFIELD HINKSON |
| Grading Pre-Inspection | 3/4/2008 | Partial Approval | WINFIELD HINKSON |
| Final | 5/23/2013 | Not Ready for Inspection | JAMES POWERS |
| Final | 7/5/2022 | Not Ready for Inspection | JAMES POWERS |
| Final | 4/10/2023 | Not Ready for Inspection | JAMES POWERS |
| Pre-Inspection | 1/21/2025 | Not Ready for Inspection | JAMES POWERS |