2866 W AVENUE 33 90065
Certificate Information: 2866 W AVENUE 33 90065
- Application / Permit
- 26047-10000-00072
- Plan Check / Job No.
- B26LA01850
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- EPLAN NEW SWIMMING POOL AND SPA PER LA CITY STANDARD PLAN
- Permit Issued
- Issued on 3/5/2026
- Issuing Office
- Current Status
- CofO Issued on 6/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2026 | GIOVANNY CHAVEZ |
| Corrections Issued | 1/21/2026 | GIOVANNY CHAVEZ |
| Plan Check Approved | 3/3/2026 | MINA HABILI |
| Issued | 3/5/2026 | APPLICANT |
| CofO in Progress | 6/17/2026 | NICHOLAS LOPEZ |
| Permit Finaled | 6/18/2026 | DEROLD HAUFF |
| CofO Issued | 6/18/2026 | DEROLD HAUFF |
| Permit Finaled | 6/18/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 1/26/2026 | ANDREA MAGANA-WITHERS |
| Grading Pre-Inspection | Cleared | 1/27/2026 | MICHAEL TEMPLE |
| Construction near power lines | Cleared | 2/28/2026 | NAOMI GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 4/9/2026 | Approved | NICHOLAS LOPEZ |
| Pre-Gunite | 4/9/2026 | Approved | NICHOLAS LOPEZ |
| Rough-Electrical | 4/9/2026 | Approved | NICHOLAS LOPEZ |
| Rough-Plumbing | 4/9/2026 | Approved | NICHOLAS LOPEZ |
| Deck | 4/17/2026 | Approved | RONNIE MEDINA |
| ELECTRICAL-Final | 5/29/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| Enclosure/Fence | 5/29/2026 | Corrections Issued | CRAIG VAUGHAN |
| Gas Piping or Gas Test | 5/29/2026 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 5/29/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 6/2/2026 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Enclosure/Fence | 6/2/2026 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 6/2/2026 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Pool Equipment Noise Test | 6/9/2026 | Approved | JONATHAN FRANCHINI |
| ELECTRICAL-Final | 6/12/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 6/12/2026 | Approved | NICHOLAS LOPEZ |
| Final | 6/12/2026 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 6/12/2026 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/12/2026 | SGSOV Not Ready | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 6/16/2026 | Approved | NICHOLAS LOPEZ |
| Final | 6/16/2026 | OK to Issue CofO | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/16/2026 | SGSOV Approved | NICHOLAS LOPEZ |