17150 W VICTORY BLVD 91316

Certificate Information: 17150 W VICTORY BLVD 91316

Application / Permit
26020-20000-00098
Plan Check / Job No.
B26VN01107
Group
Building
Type
Nonbldg-New
Sub-Type
Apartment
Primary Use
(23) Retaining Wall
Work Description
NEW RETAINING/FENCE WALLS.
Permit Issued
Issued on 4/12/2026
Issuing Office
Current Status
Issued on 4/12/2026

Permit Application Status History

Submitted 1/15/2026 APPLICANT
Assigned to Plan Check Engineer 2/5/2026 KEVIN MORALES
Assigned to Zoning Architect 2/5/2026 NEVRIK NAVASARTIAN
Corrections Issued 2/11/2026 KEVIN MORALES
Quality Review Completed 2/11/2026 EUGENE BARBEAU
Plan Check Approved 4/8/2026 KEVIN MORALES
Issued 4/12/2026 APPLICANT

Permit Application Clearance Information

Metro Rail approval Cleared 3/18/2026 JENNIFER SU
CPC Cleared 3/25/2026 ALEX VELA
ZA Case Cleared 3/25/2026 ALEX VELA
ZA Case Cleared 3/25/2026 ALEX VELA
Miscellaneous Cleared 3/26/2026 ALEX VELA
Miscellaneous Cleared 3/26/2026 ALEX VELA
Miscellaneous Cleared 3/26/2026 ALEX VELA
Miscellaneous Cleared 3/26/2026 ALEX VELA
Miscellaneous Cleared 3/26/2026 ALEX VELA
Zoning Plan Check Cleared 4/1/2026 NEVRIK NAVASARTIAN

Contact Information

Contractor Walton Construction Inc; Lic. No.: 1034491-B       ,

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/23/2026 Corrections Issued JOHN KITCKO
Pre-Inspection 4/23/2026 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 4/24/2026 Partial Approval ROBERT DAVIS
Deputy Reinf. Masonry 4/30/2026 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 4/30/2026 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 5/6/2026 Conditional Approval ROBERT DAVIS
Deputy Reinf. Masonry 5/6/2026 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 5/7/2026 Approved JOHN KITCKO
Deputy Reinf. Masonry 5/7/2026 Approved JOHN KITCKO
Footing/Foundation/Slab 5/7/2026 Not Ready for Inspection JOHN KITCKO
Reinforced Masonry Frame 5/7/2026 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 5/8/2026 Approved ROBERT DAVIS
Deputy Reinf. Masonry 5/8/2026 Approved ROBERT DAVIS
Reinforced Concrete Frame 5/8/2026 Partial Approval ROBERT DAVIS
Reinforced Masonry Frame 5/8/2026 Partial Approval ROBERT DAVIS
Reinforced Masonry Frame 5/12/2026 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 5/13/2026 Conditional Approval ROBERT DAVIS
Deputy Reinf. Masonry 5/13/2026 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 5/13/2026 Partial Approval ROBERT DAVIS
Reinforced Masonry Frame 5/13/2026 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 5/14/2026 Conditional Approval ROBERT DAVIS
Deputy Reinf. Masonry 5/14/2026 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 5/15/2026 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 5/15/2026 Conditional Approval JOHN KITCKO
Reinforced Masonry Frame 5/19/2026 Partial Approval ROBERT DAVIS
Deputy Reinf. Masonry 5/21/2026 Conditional Approval ROBERT DAVIS
Reinforced Masonry Frame 5/21/2026 Partial Approval ROBERT DAVIS
Deputy Reinf. Masonry 5/22/2026 Conditional Approval ROBERT DAVIS
Masonry Wall/Backfill 5/22/2026 Partial Approval ROBERT DAVIS
Deputy Reinf. Masonry 5/26/2026 Approved ROBERT DAVIS
Reinforced Masonry Frame 5/26/2026 Partial Approval ROBERT DAVIS
Deputy Reinf. Masonry 5/27/2026 Conditional Approval ROBERT DAVIS
Deputy Reinf. Masonry 5/28/2026 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 6/2/2026 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/4/2026 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/5/2026 Approved ROBERT DAVIS