1417 N CAPRI DR 90272
Certificate Information: 1417 N CAPRI DR 90272
- Application / Permit
- 26016-30000-03292
- Plan Check / Job No.
- B26WL00650
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior structural interior of an (e) SFD. Infill of ceiling area, laundry room kitchen and bathroom remodels. Infill of interior walls thru-out.
- Permit Issued
- Issued on 2/23/2026
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/23/2026
Permit Application Status History
| Submitted | 2/4/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 2/12/2026 | RICHARD GARCIA |
| Corrections Issued | 2/13/2026 | RICHARD GARCIA |
| Building Plans Picked Up | 2/17/2026 | APPLICANT |
| Plan Check Approved | 2/18/2026 | BEHROUZ KHOKHAR |
| Issued | 2/23/2026 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Gibbens,, Dennis Moore; Lic. No.: C23600 | 1634 OCEAN PARK BLVD SANTA MONICA, CA 90405 |
| Contractor | Valle/Reinis Builders Inc; Lic. No.: 839178-B | 11556 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
| Engineer | Hoekstra,, Travis Jon; Lic. No.: S6438 | 553 S OAK KNOLL AVE PASADENA, CA 91101 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/7/2026 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/7/2026 | Corrections Issued | KEVIN SARGSYAN |
| Wood Frame | 4/7/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/10/2026 | Partial Approval | KEVIN SARGSYAN |
| Wood Frame | 4/10/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/14/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Wood Frame | 4/14/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 4/21/2026 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/21/2026 | Approved | KEVIN SARGSYAN |
| Wood Frame | 4/21/2026 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/27/2026 | Approved | EVAN COOPER |
| Drywall Nailing | 5/7/2026 | Approved | KEVIN SARGSYAN |
| Shower Pan | 5/8/2026 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 5/13/2026 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/20/2026 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 5/29/2026 | Approved | HERBERT GIRON |