6900-6902 N KATHERINE AVE 91405
Certificate Information: 6900-6902 N KATHERINE AVE 91405
- Application / Permit
- 26016-20000-12210
- Plan Check / Job No.
- B26VN12384
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EX ATTACHED GARAGE AND PORTION OF SFD INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1). ALL WORK PER WFPP.
- Permit Issued
- Issued on 5/29/2026
- Issuing Office
- Valley
- Current Status
- Issued on 5/29/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/7/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2026 | HAYATO TSUCHIYA |
| Corrections Issued | 5/13/2026 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 5/15/2026 | APPLICANT |
| Applicant returned to address corrections | 5/22/2026 | ANGELICA DAVE |
| Plan Check Approved | 5/28/2026 | ARAMIK SHAHMIRZAIAN |
| Issued | 5/29/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/22/2026 | OSCAR GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2026 | OSCAR GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 5/22/2026 | OSCAR GUTIERREZ |
| Sewer availability | Cleared | 5/22/2026 | OSCAR GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/3/2026 | Corrections Issued | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 6/3/2026 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 6/3/2026 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 6/3/2026 | Not Ready for Inspection | VINCENT HANLEY |
| Pre-Inspection | 6/5/2026 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 6/10/2026 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 6/22/2026 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/22/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/22/2026 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/25/2026 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/25/2026 | Approved | VINCENT HANLEY |
| Insulation | 6/25/2026 | Approved | VINCENT HANLEY |
| Drywall Nailing | 6/30/2026 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Final | 7/9/2026 | Approved | VINCENT HANLEY |
| HVAC-Final | 7/9/2026 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/10/2026 | Approved | VINCENT HANLEY |
| Final | 7/10/2026 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 7/10/2026 | Approved | VINCENT HANLEY |
| HVAC-Final | 7/10/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 7/10/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/10/2026 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 7/10/2026 | Approved | VINCENT HANLEY |