1647 E 50TH ST 90011
Certificate Information: 1647 E 50TH ST 90011
- Application / Permit
- 26016-20000-08947
- Plan Check / Job No.
- B26VN08945
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan: INTERIOR AND EXTERIOR REMODEL TO (E) DUPLEX.
- Permit Issued
- Issued on 4/30/2026
- Issuing Office
- Current Status
- Issued on 4/30/2026
Permit Application Status History
| Submitted | 4/7/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2026 | DANIEL YIP |
| Corrections Issued | 4/9/2026 | DANIEL YIP |
| Applicant returned to address corrections | 4/25/2026 | DANIEL YIP |
| Plan Check Approved | 4/29/2026 | DANIEL YIP |
| Issued | 4/30/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/23/2026 | CINDY QI |
| Sewer availability | Cleared | 4/23/2026 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2026 | ROSE STEIN-WENDT |
Contact Information
| Contractor | Cr Builders Llc; Lic. No.: 1131278-B | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/11/2026 | No Access for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 5/11/2026 | No Access for Inspection | SABAS ALONSO |
| HVAC-Rough | 5/11/2026 | No Access for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 5/11/2026 | No Access for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/12/2026 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 5/12/2026 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2026 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 6/1/2026 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 6/1/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/4/2026 | Approved | SABAS ALONSO |
| HVAC-Rough | 6/4/2026 | Corrections Issued | SABAS ALONSO |