24118 W HIGHLANDER ROAD 91307
Certificate Information: 24118 W HIGHLANDER ROAD 91307
- Application / Permit
- 26016-20000-03471
- Plan Check / Job No.
- B26VN03303
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior and exterior remodel, convert attached storage to part of the SFD. All work per WFPP
- Permit Issued
- Issued on 2/5/2026
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 4/29/2026
Permit Application Status History
| Submitted | 2/5/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2026 | NAREG ATARIAN |
| Plan Check Approved | 2/5/2026 | NAREG ATARIAN |
| Issued | 2/5/2026 | APPLICANT |
| Permit Finaled | 4/28/2026 | JEFFREY HARTLINE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 2/23/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 2/23/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 2/23/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Sewer | 2/23/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Underground Mechanical | 2/23/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/25/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 2/25/2026 | Approved | JEFFREY HARTLINE |
| Gas Test | 2/25/2026 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 2/25/2026 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 2/25/2026 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 3/2/2026 | Partial Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 3/5/2026 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 3/5/2026 | Approved | JEFFREY HARTLINE |
| Insulation | 3/5/2026 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 3/5/2026 | Partial Approval | JEFFREY HARTLINE |
| Drywall Nailing | 3/10/2026 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 3/10/2026 | Partial Approval | JEFFREY HARTLINE |
| ELECTRICAL-Final | 4/28/2026 | Approved | JEFFREY HARTLINE |
| Final | 4/28/2026 | Permit Finaled | JEFFREY HARTLINE |
| Grounding or Bonding | 4/28/2026 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 4/28/2026 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 4/28/2026 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 4/28/2026 | SGSOV Approved | JEFFREY HARTLINE |
| Service/Power Release | 4/28/2026 | Approved | JEFFREY HARTLINE |
| Smoke Detectors | 4/28/2026 | Approved | JEFFREY HARTLINE |