7049 W ST ESTABAN ST 91042
Certificate Information: 7049 W ST ESTABAN ST 91042
- Application / Permit
- 26016-20000-02712
- Plan Check / Job No.
- B26VN02531
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: DET. GARAGE CONVERSION TO ADU: 3 PER GC66323(a)(1).
- Permit Issued
- Issued on 4/23/2026
- Issuing Office
- Current Status
- Issued on 4/23/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/2/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2026 | YILE TIAN |
| Corrections Issued | 2/9/2026 | YILE TIAN |
| Applicant returned to address corrections | 3/25/2026 | YILE TIAN |
| Applicant returned to address corrections | 4/2/2026 | LUKE GONZALES |
| Plan Check Approved | 4/23/2026 | LUKE GONZALES |
| Issued | 4/23/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2026 | ROSE STEIN-WENDT |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2026 | ROSE STEIN-WENDT |
| Sewer availability | Cleared | 3/9/2026 | ROSE STEIN-WENDT |
| Specific Plan | Cleared | 3/19/2026 | JOSHUA ORDONEZ |
| Grading Pre-Inspection | Cleared | 4/17/2026 | LUKE GONZALES |
Contact Information
| Contractor | Green Tech Remodeling & Design Inc; Lic. No.: 1055131-B | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Service/Power Release | 7/16/2026 Time Frame: 2-4 |
Inspection Request History
| Deputy Drilled-In Anchors | 5/28/2026 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 5/28/2026 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 5/28/2026 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 6/4/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 6/4/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 6/8/2026 | Approved | DAVID ANDERSON |
| Green Building Rough | 6/8/2026 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 6/8/2026 | Approved | DAVID ANDERSON |
| Insulation | 6/10/2026 | Approved | DAVID ANDERSON |
| Drywall Nailing | 6/16/2026 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 6/16/2026 | Partial Approval | DAVID ANDERSON |
| Sewer | 6/16/2026 | Approved | DAVID ANDERSON |
| Shower Pan | 6/30/2026 | Approved | DAVID MATSON |
| Gas Test | 7/2/2026 | Corrections Issued | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/2/2026 | Approved | DAVID ANDERSON |
| Underground Mechanical | 7/2/2026 | Corrections Issued | DAVID ANDERSON |
| Gas Test | 7/14/2026 | Partial Approval | DAVID MATSON |
| Underground Mechanical | 7/14/2026 | Partial Approval | DAVID MATSON |