8334-8336 N CAPISTRANO AVE 91304

Certificate Information: 8334-8336 N CAPISTRANO AVE 91304

Application / Permit
26016-20000-02568
Plan Check / Job No.
B26VN02353
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
Permit Issued
Issued on 5/18/2026
Issuing Office
Valley
Current Status
Issued on 5/18/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/28/2026 APPLICANT
Assigned to Plan Check Engineer 2/2/2026 ARTIN ZARUKIAN
Corrections Issued 2/3/2026 ARTIN ZARUKIAN
Building Plans Picked Up 3/2/2026 APPLICANT
Applicant returned to address corrections 3/31/2026 MINA HABILI
Applicant returned to address corrections 5/1/2026 HAYATO TSUCHIYA
Plan Check Approved 5/18/2026 OMAR GARNICA
Issued 5/18/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/2/2026 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 3/2/2026 MICHAEL BROWN
Sewer availability Cleared 3/2/2026 MICHAEL BROWN
Grading Pre-Inspection Cleared 5/1/2026 ALEXANDER HELFER

Contact Information

Contractor H T Constructions; Lic. No.: 580511-B 8426 NATALIE LN      WEST HILLS, CA 91304

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/22/2026 Partial Approval JOHN KIDWELL
Deputy Drilled-In Anchors 5/22/2026 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 5/22/2026 Approved JOHN KIDWELL
Footing/Foundation/Slab 5/22/2026 Approved JOHN KIDWELL
Green Building Rough 5/22/2026 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 5/22/2026 Approved JOHN KIDWELL
BUILDING-Rough-Frame 6/3/2026 Approved JEFFREY HARTLINE
Green Building Rough 6/3/2026 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 6/3/2026 Partial Approval JEFFREY HARTLINE
Wood Frame 6/3/2026 Approved JEFFREY HARTLINE
Insulation 6/11/2026 Approved JEFFREY HARTLINE
Drywall Nailing 7/6/2026 Approved JEFFREY HARTLINE