9513 N ENCINO AVE 91325

Certificate Information: 9513 N ENCINO AVE 91325

Application / Permit
26016-20000-02385
Plan Check / Job No.
B26VN02157
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO BEDROOM TO (E) SFD
Permit Issued
Issued on 3/3/2026
Issuing Office
Current Status
CofO Issued on 7/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2026 APPLICANT
Assigned to Plan Check Engineer 1/30/2026 JEROME MAGAT PALMA
Corrections Issued 1/31/2026 JEROME MAGAT PALMA
Building Plans Picked Up 2/6/2026 APPLICANT
Plan Check Approved 3/3/2026 SERGIO MUNIZ
Issued 3/3/2026 APPLICANT
CofO in Progress 6/25/2026 CHRISTOPHER ROJAS
Permit Finaled 7/9/2026 RUBEN SALAS
CofO Issued 7/9/2026 RUBEN SALAS
Permit Finaled 7/9/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/12/2026 CINDY QI
Sewer availability Cleared 2/12/2026 CINDY QI
Grading Pre-Inspection Cleared 2/25/2026 MANUEL TEJADA

Contact Information

Contractor 5 Stars Home Remodeling Inc; Lic. No.: 1058712-B 22647 VENTURA BLVD UNIT 655      WOODLAND HILLS, CA 91364
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 1792 PEREGRINE CT      SIMI VALLEY, CA 93065

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/24/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/5/2026 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/5/2026 Approved CHRISTOPHER ROJAS
HVAC-Rough 5/5/2026 Approved CHRISTOPHER ROJAS
Insulation 5/11/2026 Approved JOSE AVILA
Interior/Exterior Lathing 5/11/2026 Approved JOSE AVILA
Drywall Nailing 5/15/2026 Approved JOSE AVILA
BUILDING-Rough-Frame 6/15/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Final 6/15/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 6/15/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 6/15/2026 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 6/15/2026 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 6/15/2026 No Access for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/17/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 6/17/2026 Approved CHRISTOPHER ROJAS
Final 6/24/2026 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 6/24/2026 Approved CHRISTOPHER ROJAS
Smoke Detectors 6/24/2026 Approved CHRISTOPHER ROJAS