7658 RADFORD AVE 91605
Certificate Information: 7658 RADFORD AVE 91605
- Application / Permit
- 26016-20000-02283
- Plan Check / Job No.
- B26VN02075
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED GARAGE WITH 'SAUNA BATH' INTO ACCESSORY DWELLLING UNIT PER GCS 66323(a)(1). ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/10/2026
- Issuing Office
- Current Status
- Issued on 2/10/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/26/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2026 | HAYATO TSUCHIYA |
| Corrections Issued | 1/29/2026 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 1/30/2026 | APPLICANT |
| Applicant returned to address corrections | 2/10/2026 | GIOVANNY CHAVEZ |
| Plan Check Approved | 2/10/2026 | ALEC MOUSAKHANIAN |
| Issued | 2/10/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/6/2026 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2026 | DARIN LAM |
| Sewer availability | Cleared | 2/6/2026 | DARIN LAM |
| Clean Up Green Up | Cleared | 2/10/2026 | DANIEL CORONADO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/11/2026 | Approved | MATTHEW NELSON |
| Insulation | 3/18/2026 | Not Ready for Inspection | MATTHEW NELSON |
| Underground Mechanical | 3/18/2026 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2026 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2026 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/14/2026 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/14/2026 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/14/2026 | Approved | MATTHEW NELSON |
| HVAC-Rough | 4/14/2026 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 4/14/2026 | Not Ready for Inspection | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 4/14/2026 | Approved | MATTHEW NELSON |
| Wood Frame | 4/14/2026 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/29/2026 | Approved | MATTHEW NELSON |
| HVAC-Rough | 4/29/2026 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/29/2026 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 4/29/2026 | Approved | MATTHEW NELSON |
| Insulation | 5/1/2026 | Approved | MATTHEW NELSON |
| Drywall Nailing | 5/4/2026 | Approved | MATTHEW NELSON |
| Shower Pan | 5/26/2026 | Approved | MATTHEW NELSON |