3241-3243 S SHERBOURNE DR 90034
Certificate Information: 3241-3243 S SHERBOURNE DR 90034
- Application / Permit
- 26016-20000-02252
- Plan Check / Job No.
- B26VN02049
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1). ADU ADDRESS IS 3241 1/2 S SHERBOURNE DR WHICH FALLS IN RANGE OF (E) DUPLEX.
- Permit Issued
- Issued on 2/23/2026
- Issuing Office
- Valley
- Current Status
- Issued on 2/23/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/26/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2026 | JEROME MAGAT PALMA |
| Corrections Issued | 1/29/2026 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/30/2026 | APPLICANT |
| Applicant returned to address corrections | 2/17/2026 | OMAR GARNICA |
| Issued | 2/23/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/3/2026 | JEFF LOREDO |
| Sewer availability | Cleared | 2/3/2026 | JEFF LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2026 | JEFF LOREDO |
Contact Information
| Contractor | We Build Green Inc; Lic. No.: 1073455-B | 23906 GILMORE WEST HILLS, CA 91307 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/4/2026 | Not Ready for Inspection | WILBER ROSALES |
| Underground Mechanical | 3/4/2026 | Approved | WILBER ROSALES |
| Deputy Drilled-In Anchors | 3/26/2026 | Conditional Approval | DAVID FEILER |
| Footing/Foundation/Slab | 4/3/2026 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 5/11/2026 | Approved | KIRK SANDERS |
| HVAC-Rough | 5/11/2026 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 5/11/2026 | Approved | KIRK SANDERS |
| Underground Mechanical | 5/11/2026 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2026 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 5/14/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Insulation | 5/18/2026 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2026 | Approved | WILBER ROSALES |
| Green Building Rough | 5/20/2026 | Not Ready for Inspection | WILBER ROSALES |
| BUILDING-Rough-Frame | 6/2/2026 | Approved | WILBER ROSALES |
| Green Building Rough | 6/2/2026 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 6/2/2026 | Partial Approval | WILBER ROSALES |
| Shower Pan | 6/2/2026 | Approved | WILBER ROSALES |
| Insulation | 6/5/2026 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 6/9/2026 | Approved | ANTHONY EGSON |
| Drywall Nailing | 6/11/2026 | Approved | WILBER ROSALES |