10558 W RIVERSIDE DR 91602
Certificate Information: 10558 W RIVERSIDE DR 91602
- Application / Permit
- 26016-20000-02180
- Plan Check / Job No.
- B26VN01972
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Beauty Shop or Parlor
- Work Description
- ePlan: CHANGE OF USE AND TENANT IMPROVEMENT TO EXISTING OFFICE TO CREATE BEAUTY SALON. NEW FINISHES, MILLWORK AND UPGRADES TO EXISTING BATHROOM.
- Permit Issued
- Issued on 3/18/2026
- Issuing Office
- Current Status
- CofO Issued on 4/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2026 | GEORGE ALVAREZ |
| Corrections Issued | 2/2/2026 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 2/14/2026 | EDWIN MARTINEZ |
| Applicant returned to address corrections | 2/25/2026 | KELVIN CHUONG |
| Applicant returned to address corrections | 3/5/2026 | KELVIN CHUONG |
| Plan Check Approved | 3/16/2026 | KELVIN CHUONG |
| Issued | 3/18/2026 | APPLICANT |
| CofO in Progress | 4/7/2026 | DEANDRE HOFFMAN |
| Permit Finaled | 4/7/2026 | JEFFREY DURAN |
| Permit Finaled | 4/7/2026 | JEFFREY DURAN |
| CofO Issued | 4/7/2026 | JEFFREY DURAN |
Permit Application Clearance Information
| ZA Case | Cleared | 2/5/2026 | MAYELA VILLA |
| Address approval | Cleared | 2/18/2026 | ROSE STEIN-WENDT |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2026 | ROSE STEIN-WENDT |
| Sewer availability | Cleared | 2/18/2026 | ROSE STEIN-WENDT |
Contact Information
| Architect | Royalty,, Stuart A; Lic. No.: NA25881 | , |
| Contractor | Mission Construction Inc; Lic. No.: 818440-B | , |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 3/19/2026 | Partial Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 3/19/2026 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 3/19/2026 | Approved | DEANDRE HOFFMAN |
| Wood Frame | 3/19/2026 | Approved | DEANDRE HOFFMAN |
| Final | 3/31/2026 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 4/7/2026 | OK to Issue CofO | DEANDRE HOFFMAN |