1142 S ABBOT KINNEY BLVD 90291

Certificate Information: 1142 S ABBOT KINNEY BLVD 90291

Application / Permit
26016-20000-01551
Plan Check / Job No.
B26VN01375
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CHANGE OF USE FROM (E) TAKE-OUT RESTAURANT TO (N) RESTAURANT. REMODEL KITCHEN, LOBBY AND RESTROOM. INSTALL NEW EQUIPTMENT AND SEATING.
Permit Issued
Issued on 3/13/2026
Issuing Office
Valley
Current Status
CofO Issued on 5/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2026 APPLICANT
Assigned to Plan Check Engineer 1/22/2026 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 1/24/2026 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 1/26/2026 APPLICANT
Applicant returned to address corrections 2/3/2026 ROSENDO MEDINA
Plan Check Approved 3/13/2026 ROSENDO MEDINA
Issued 3/13/2026 APPLICANT
CofO in Progress 5/14/2026 FARHAD DADBIN
Permit Finaled 5/15/2026 VASIL MIHALEV
CofO Issued 5/15/2026 VASIL MIHALEV
Permit Finaled 5/15/2026 VASIL MIHALEV

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/26/2026 JESUS CISNEROS
Sewer availability Cleared 1/26/2026 JESUS CISNEROS
Coastal Zone Cleared 2/12/2026 NOAH MCCOY
ZA Case Cleared 2/12/2026 NOAH MCCOY
ZA Case Cleared 2/12/2026 NOAH MCCOY
ZA Case Cleared 2/12/2026 NOAH MCCOY
Specific Plan Cleared 2/18/2026 LUIS LOPEZ
Food Service Establishment Cleared 2/26/2026 LUIS LUVANO
Specific Plan Cleared 3/10/2026 EDER ROMERO
Specific Plan Cleared 3/10/2026 EDER ROMERO
Food establishment approval Cleared 3/13/2026 LACDHS APPROVED

Contact Information

Contractor Rank-1 Construction Co; Lic. No.: 960933-B 1698 BRIDGEPORT AVENUE      CLAREMONT, CA 91711

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 3/18/2026 Conditional Approval CASIMIR BRITTON
Excavation/Setback/Form/Re-Bar 3/27/2026 Partial Approval FARHAD DADBIN
Drywall Nailing 4/3/2026 Not Ready for Inspection FARHAD DADBIN
Insulation 4/3/2026 Partial Approval FARHAD DADBIN
Drywall Nailing 4/6/2026 Not Ready for Inspection FARHAD DADBIN
Insulation 4/6/2026 Approved FARHAD DADBIN
Drywall Nailing 4/9/2026 Partial Approval DANIEL ARMENTA
Insulation 4/9/2026 Partial Approval DANIEL ARMENTA
METHANE-Final 4/21/2026 Approved FARHAD DADBIN
METHANE-Rough 4/21/2026 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 4/21/2026 SGSOV Not Ready FARHAD DADBIN
Smoke Detectors 4/21/2026 Not Ready for Inspection FARHAD DADBIN
Wood Frame 4/21/2026 Not Ready for Inspection FARHAD DADBIN
Final 4/28/2026 Not Ready for Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 4/28/2026 SGSOV Approved FARHAD DADBIN
Smoke Detectors 4/28/2026 Approved FARHAD DADBIN
Wood Frame 4/28/2026 Approved FARHAD DADBIN
Final 5/14/2026 OK to Issue CofO FARHAD DADBIN