853 E SUNSET AVE 90291

Certificate Information: 853 E SUNSET AVE 90291

Application / Permit
26016-10000-07696
Plan Check / Job No.
B26LA08606
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*eplan* Conversion of (E) deatched garage to detached accessory dwelling unit per state law
Permit Issued
Issued on 6/10/2026
Issuing Office
Current Status
Issued on 6/10/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/11/2026 APPLICANT
Assigned to Plan Check Engineer 3/19/2026 ALEXIS VERDUGO
Assigned to Zoning Architect 3/19/2026 VIVIANA VIVERO
Corrections Issued 3/23/2026 ALEXIS VERDUGO
Quality Review Completed 3/27/2026 ARMEN JIVALAGIAN
Applicant returned to address corrections 4/29/2026 ALEXIS VERDUGO
Applicant returned to address corrections 5/13/2026 ALEXIS VERDUGO
Plan Check Approved 6/9/2026 ALEXIS VERDUGO
Issued 6/10/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/1/2026 DAVID LOPEZ
Zoning Plan Check Cleared 5/1/2026 VIVIANA VIVERO
Eng Process Fee Ord 176,300 Cleared 6/3/2026 ANDREA RIVERA
Sewer availability Cleared 6/3/2026 ANDREA RIVERA

Contact Information

Contractor Castillo Construction; Lic. No.: 960211-B       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Green Building Rough 7/23/2026   
BUILDING-Rough-Frame 7/23/2026   

Inspection Request History

ELECTRICAL-Rough 6/23/2026 Approved RUBEN RIVAS
Footing/Foundation/Slab 6/23/2026 Approved RUBEN RIVAS
HVAC-Rough 6/23/2026 Not Ready for Inspection RUBEN RIVAS
PLUMBING-Rough 6/23/2026 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Rough 7/7/2026 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 7/7/2026 Corrections Issued RUBEN RIVAS
PLUMBING-Rough 7/7/2026 Corrections Issued RUBEN RIVAS
ELECTRICAL-Rough 7/14/2026 Not Ready for Inspection RUBEN RIVAS
PLUMBING-Rough 7/14/2026 Approved RUBEN RIVAS
BUILDING-Rough-Frame 7/20/2026 Partial Approval RUBEN RIVAS
ELECTRICAL-Rough 7/20/2026 Approved RUBEN RIVAS
Green Building Rough 7/20/2026 Not Ready for Inspection RUBEN RIVAS