5189 W ADAMS BLVD 90016

Certificate Information: 5189 W ADAMS BLVD 90016

Application / Permit
26016-10000-05049
Plan Check / Job No.
B26LA07061
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Doctor's or Dentist's Office
Work Description
eplan INITIAL TENANT IMPROVEMENT & CHANGE OF USE FROM (E) RETAIL TO (N) DENTAL OFFICE. 4,700 SQ FT
Permit Issued
Issued on 5/7/2026
Issuing Office
Current Status
Issued on 5/7/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/3/2026 APPLICANT
Assigned to Plan Check Engineer 3/12/2026 LAMAR DAVIS
Assigned to Zoning Architect 3/12/2026 MEGAN KOLP
Corrections Issued 3/19/2026 LAMAR DAVIS
Quality Review Completed 3/26/2026 ARMEN JIVALAGIAN
Applicant returned to address corrections 4/15/2026 LAMAR DAVIS
Plan Check Approved 5/7/2026 LAMAR DAVIS
Issued 5/7/2026 APPLICANT

Permit Application Clearance Information

"D" conditions Cleared 4/14/2026 ASHLEY MACIAS
Miscellaneous Cleared 4/14/2026 ASHLEY MACIAS
Miscellaneous Cleared 4/14/2026 ASHLEY MACIAS
Miscellaneous Cleared 4/14/2026 ASHLEY MACIAS
Miscellaneous Cleared 4/14/2026 ASHLEY MACIAS
Miscellaneous Cleared 4/14/2026 ASHLEY MACIAS
Miscellaneous Cleared 4/14/2026 ASHLEY MACIAS
Miscellaneous Cleared 4/14/2026 ASHLEY MACIAS
ZA Case Cleared 4/14/2026 ASHLEY MACIAS
Green Code Cleared 4/24/2026 AARON COSTA
Community Plan Implem. Overlay Cleared 4/28/2026 ISAIAH ROSS
DAS Clearance Cleared 4/28/2026 LAMAR DAVIS
Historic Resource Verification Cleared 4/28/2026 YASMINE BASHIRI
Redevelopment Project Area Cleared 4/28/2026 YASMINE BASHIRI
Zoning Plan Check Cleared 5/6/2026 MEGAN KOLP

Contact Information

Architect Abdelsayed,, Marc A; Lic. No.: C38176 280 VIA LINDA VISTA      REDONDO BEACH, CA 90277
Contractor J C Galvan Company Inc; Lic. No.: 1021270-B       ,

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 5/15/2026 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 5/19/2026 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 5/19/2026 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 5/21/2026 Partial Approval IAN BLINN
T-Bar Ceiling 6/10/2026 Approved CHRISTOPHER BLACKWOOD