8334-8336 N TUNNEY AVE 91324

Certificate Information: 8334-8336 N TUNNEY AVE 91324

Application / Permit
26016-10000-04602
Plan Check / Job No.
B26LA06406
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERSION OF (E) ATTACHED GARAGE INTO ADU. ALL CONSTRUCTION WORK PER WFPP.
Permit Issued
Issued on 3/12/2026
Issuing Office
Metro
Current Status
CofO in Progress on 6/25/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/19/2026 APPLICANT
Assigned to Plan Check Engineer 2/25/2026 NEHEMIAS RAMOS
Corrections Issued 2/26/2026 NEHEMIAS RAMOS
Building Plans Picked Up 2/27/2026 APPLICANT
Plan Check Approved 3/12/2026 CRISTINA SALAZAR
Plan Check Approved 3/12/2026 CRISTINA SALAZAR
Issued 3/12/2026 APPLICANT
CofO in Progress 6/25/2026 JEFFREY HARTLINE
CofO in Progress 6/25/2026 JEFFREY HARTLINE

Permit Application Clearance Information

Address approval Cleared 3/6/2026 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 3/6/2026 MARKOS PEREZ-BRAN
Sewer availability Cleared 3/6/2026 MARKOS PEREZ-BRAN
Hold Cleared 4/7/2026 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Badilla, Garces, Maria Elena; Lic. No.: C81817 945 N GLENN AVE      ONTARIO, CA 91764

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/8/2026 Corrections Issued JEFFREY HARTLINE
Underground Mechanical 4/8/2026 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 4/20/2026 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Rough 4/20/2026 Approved JEFFREY HARTLINE
HVAC-Rough 4/20/2026 Approved JEFFREY HARTLINE
PLUMBING-Rough 4/20/2026 Approved JEFFREY HARTLINE
Insulation 4/24/2026 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 4/24/2026 Partial Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 4/29/2026 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 4/29/2026 Approved JEFFREY HARTLINE
Green Building Rough 4/29/2026 Approved JEFFREY HARTLINE
Drywall Nailing 5/5/2026 Approved JUAN ALVARADO
ELECTRICAL-Final 6/24/2026 Approved JEFFREY HARTLINE
Final 6/24/2026 Partial Approval JEFFREY HARTLINE
Green Building Final 6/24/2026 Approved JEFFREY HARTLINE
HVAC-Final 6/24/2026 Approved JEFFREY HARTLINE
PLUMBING-Final 6/24/2026 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 6/24/2026 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 6/24/2026 Approved JEFFREY HARTLINE
Gas Test 6/30/2026 Corrections Issued CHRISTOPHER WILSON
Gas Test 7/6/2026 Approved JEFFREY HARTLINE
Pre-Inspection 7/6/2026 Partial Approval JEFFREY HARTLINE