1744-1746 S CARMONA AVE 90019
Certificate Information: 1744-1746 S CARMONA AVE 90019
- Application / Permit
- 26016-10000-03100
- Plan Check / Job No.
- B26LA03996
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan. Interior / exterior remodel to (e) duplex to add a bedroom and a bathroom to each unit ; remodel bathrooms and kitchens
- Permit Issued
- Issued on 2/13/2026
- Issuing Office
- Current Status
- Issued on 2/13/2026
Permit Application Status History
| Submitted | 2/3/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2026 | JOHNPAUL ISIP |
| Corrections Issued | 2/9/2026 | JOHNPAUL ISIP |
| Plan Check Approved | 2/12/2026 | REZA HAGHIGHAT |
| Issued | 2/13/2026 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/11/2026 | CINDY QI |
| Tenant Habitability Plan | Cleared | 2/11/2026 | HUGO GARRIDO GARZA |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2026 | TONY CHIANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/26/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| ELECTRICAL-Rough | 3/26/2026 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Rough | 3/26/2026 | Corrections Issued | WILLIAM SIERRA |
| Pre-Inspection | 3/31/2026 | Partial Inspection | BRENDAN MORELLI |
| Underground Mechanical | 3/31/2026 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 4/3/2026 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 4/3/2026 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 4/3/2026 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 4/3/2026 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 4/10/2026 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 4/10/2026 | Partial Approval | BRENDAN MORELLI |
| Shower Pan | 4/10/2026 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 4/22/2026 | Approved | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 4/23/2026 | Approved | WILLIAM SIERRA |
| Special/Order Compliance | 4/23/2026 | Corrections Issued | WILLIAM SIERRA |
| Drywall Nailing | 6/18/2026 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 6/18/2026 | Corrections Issued | JUSTIN HAWLEY |
| Final | 7/8/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 7/8/2026 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 7/8/2026 | Approved | DAVID WILLIAMS |