500 W 66TH ST 90044
Certificate Information: 500 W 66TH ST 90044
- Application / Permit
- 26016-10000-02308
- Plan Check / Job No.
- B26LA02752
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. CONVERT DETACHED STORAGE AND RECREATION ROOM TO ADU PER STATE LAW.
- Permit Issued
- Issued on 3/20/2026
- Issuing Office
- Current Status
- Issued on 3/20/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/26/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2026 | DANIEL SMILEY |
| Corrections Issued | 2/3/2026 | DANIEL SMILEY |
| Applicant returned to address corrections | 3/13/2026 | CARLOS MONTES |
| Plan Check Approved | 3/20/2026 | CARLOS MONTES |
| Issued | 3/20/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/20/2026 | MICHAEL BROWN |
| Sewer availability | Cleared | 2/20/2026 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2026 | MICHAEL BROWN |
| Construction near power lines | Cleared | 2/26/2026 | NAOMI GARCIA |
| Construction within easement | Cleared | 2/26/2026 | NAOMI GARCIA |
Contact Information
| Contractor | Wallz Construction; Lic. No.: 1133614-B | , |
| Contractor | Wallz Inc; Lic. No.: 1133614-B | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/17/2026 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 4/17/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| MERV13>=Rough | 4/17/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/30/2026 | Not Ready for Inspection | LUIS CASTRO |
| Green Building Rough | 4/30/2026 | Not Ready for Inspection | LUIS CASTRO |
| MERV13>=Rough | 4/30/2026 | Not Ready for Inspection | LUIS CASTRO |
| BUILDING-Rough-Frame | 5/13/2026 | Not Ready for Inspection | LUIS CASTRO |
| Green Building Rough | 5/13/2026 | Not Ready for Inspection | LUIS CASTRO |
| MERV13>=Rough | 5/13/2026 | Not Ready for Inspection | LUIS CASTRO |
| BUILDING-Rough-Frame | 5/18/2026 | Corrections Issued | RAUL BARAJAS |
| Green Building Rough | 5/18/2026 | Not Ready for Inspection | RAUL BARAJAS |
| MERV13>=Rough | 5/18/2026 | Not Ready for Inspection | RAUL BARAJAS |
| Pre-Inspection | 5/18/2026 | Approved | RAUL BARAJAS |