12121 W OLYMPIC BLVD Unit 3 90064
Certificate Information: 12121 W OLYMPIC BLVD Unit 3 90064
- Application / Permit
- 26016-10000-01365
- Plan Check / Job No.
- B26LA01462
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Cosmetological Establishment
- Work Description
- ePlan: Change of use from (E) office to cosmetological services.
- Permit Issued
- Issued on 4/8/2026
- Issuing Office
- Current Status
- Issued on 4/8/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/21/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2026 | CARLOS MONTES |
| Corrections Issued | 1/22/2026 | CARLOS MONTES |
| Applicant returned to address corrections | 2/13/2026 | SHANGQIN XIE |
| Applicant returned to address corrections | 2/19/2026 | SHANGQIN XIE |
| Applicant returned to address corrections | 3/2/2026 | SHANGQIN XIE |
| Plan Check Approved | 3/30/2026 | RICARDO RAMIREZ |
| Plan Check Approved | 4/3/2026 | RICARDO RAMIREZ |
| Issued | 4/8/2026 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 2/13/2026 | GEORGIA SMITH |
| CPC | Cleared | 2/13/2026 | GEORGIA SMITH |
| ZA Case | Cleared | 2/13/2026 | GEORGIA SMITH |
| ZA Case | Cleared | 2/13/2026 | GEORGIA SMITH |
| ZA Case | Cleared | 2/13/2026 | GEORGIA SMITH |
| ZI | Cleared | 2/13/2026 | GEORGIA SMITH |
| Specific Plan | Cleared | 2/17/2026 | HAMID GHAEMMAGHAMI |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2026 | MICHAEL BROWN |
| Sewer availability | Cleared | 3/3/2026 | MICHAEL BROWN |
| Specific Plan | Cleared | 3/25/2026 | KYLE WINSTON |
Contact Information
| Architect | Jaffar,, Luma; Lic. No.: C38314 | 2008 CANONERO DRIVE AUSTIN, TX 787462110 |
| Contractor | Renault And Moran Construction Llc; Lic. No.: 1038156-B | , |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/12/2026 | Not Ready for Inspection | CASIMIR BRITTON |
| Light Gage Steel Frame | 6/8/2026 | Corrections Issued | CASIMIR BRITTON |
| Light Gage Steel Frame | 6/18/2026 | Partial Approval | CASIMIR BRITTON |
| Insulation | 6/23/2026 | Approved | CASIMIR BRITTON |
| Drywall Nailing | 6/25/2026 | Partial Approval | CASIMIR BRITTON |
| Light Gage Steel Frame | 6/25/2026 | Corrections Issued | CASIMIR BRITTON |