719 W 118TH ST 90044
Certificate Information: 719 W 118TH ST 90044
- Application / Permit
- 26016-10000-00744
- Plan Check / Job No.
- B26LA00704
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. Convert existing detached garage into ADU per State Law. All work per WFPP
- Permit Issued
- Issued on 3/3/2026
- Issuing Office
- Current Status
- Issued on 3/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/20/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2026 | DANIEL SANJUAN |
| Corrections Issued | 1/27/2026 | DANIEL SANJUAN |
| Applicant returned to address corrections | 2/24/2026 | NEHEMIAS RAMOS |
| Plan Check Approved | 2/28/2026 | NEHEMIAS RAMOS |
| Issued | 3/3/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2026 | JESUS CISNEROS |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2026 | JESUS CISNEROS |
| Sewer availability | Cleared | 2/11/2026 | JESUS CISNEROS |
Contact Information
| Contractor | Golden Estate Builders Inc; Lic. No.: 1113809-B | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| BUILDING-Rough-Frame | 6/9/2026 |
| Green Building Rough | 6/9/2026 |
| Gas Test | 6/9/2026 |
| PLUMBING-Rough | 6/9/2026 |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2026 |
| ELECTRICAL-Rough | 6/9/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/26/2026 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 3/26/2026 | Corrections Issued | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 3/31/2026 | Approved | BEN MOLSTAD |
| Footing/Foundation/Slab | 3/31/2026 | Partial Approval | BEN MOLSTAD |
| Sewer | 4/10/2026 | Partial Approval | BEN MOLSTAD |
| Underground Mechanical | 4/10/2026 | Partial Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 4/15/2026 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 4/15/2026 | Partial Approval | BEN MOLSTAD |
| Sewer | 4/15/2026 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 5/5/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 5/5/2026 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Rough | 5/5/2026 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 5/11/2026 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 5/11/2026 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 5/11/2026 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 5/11/2026 | Corrections Issued | BEN MOLSTAD |
| MERV13>=Rough | 5/11/2026 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 5/11/2026 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 5/13/2026 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 5/13/2026 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 5/13/2026 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 5/13/2026 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 5/13/2026 | Corrections Issued | BEN MOLSTAD |