817-819 W 79TH ST 90044
Certificate Information: 817-819 W 79TH ST 90044
- Application / Permit
- 26014-70000-01158
- Plan Check / Job No.
- B26SL00415
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- One story addition (743sf) to single family dwelling to create ADU per city ordinance. Allocate portion of existing dwelling (253sf) to ADU (996sf). Remodel existing dwelling to relocate kitchen and add new bathroom. Redrywall existing dwelling along with change out of existing windows and doors.
- Permit Issued
- Issued on 4/16/2026
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 4/16/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/31/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 4/3/2026 | RICARDO RAMIREZ |
| Corrections Issued | 4/4/2026 | RICARDO RAMIREZ |
| Building Plans Picked Up | 4/7/2026 | APPLICANT |
| Issued | 4/16/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2026 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 4/8/2026 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2026 | MICHAEL BROWN |
| Sewer availability | Cleared | 4/13/2026 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Interior/Exterior Lathing | 6/26/2026 |
Inspection Request History
| Deputy Drilled-In Anchors | 4/29/2026 | Conditional Approval | ALEX COLIN |
| Excavation/Setback/Form/Re-Bar | 4/29/2026 | Approved | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 4/29/2026 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 5/8/2026 | Approved | JOHN QUINTANILLA |
| Wood Frame | 5/8/2026 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2026 | Approved | JOHN QUINTANILLA |
| Insulation | 5/11/2026 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2026 | Approved | RAUL BARAJAS |
| Sewer | 6/5/2026 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 6/5/2026 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 6/11/2026 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 6/11/2026 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 6/15/2026 | Approved | BRENDAN MORELLI |
| Green Building Rough | 6/15/2026 | Approved | BRENDAN MORELLI |
| Insulation | 6/17/2026 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 6/17/2026 | Partial Approval | ALEX COLIN |
| Drywall Nailing | 6/24/2026 | Approved | ALEX COLIN |