817-819 W 79TH ST 90044

Certificate Information: 817-819 W 79TH ST 90044

Application / Permit
26014-70000-01158
Plan Check / Job No.
B26SL00415
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One story addition (743sf) to single family dwelling to create ADU per city ordinance. Allocate portion of existing dwelling (253sf) to ADU (996sf). Remodel existing dwelling to relocate kitchen and add new bathroom. Redrywall existing dwelling along with change out of existing windows and doors.
Permit Issued
Issued on 4/16/2026
Issuing Office
South Los Angeles
Current Status
Issued on 4/16/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/31/2026 APPLICANT
Assigned to Plan Check Engineer 4/3/2026 RICARDO RAMIREZ
Corrections Issued 4/4/2026 RICARDO RAMIREZ
Building Plans Picked Up 4/7/2026 APPLICANT
Issued 4/16/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/8/2026 MICHAEL BROWN
Roof/Waste drainage to street Cleared 4/8/2026 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 4/13/2026 MICHAEL BROWN
Sewer availability Cleared 4/13/2026 MICHAEL BROWN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Interior/Exterior Lathing 6/26/2026   

Inspection Request History

Deputy Drilled-In Anchors 4/29/2026 Conditional Approval ALEX COLIN
Excavation/Setback/Form/Re-Bar 4/29/2026 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 4/29/2026 Approved JOHN QUINTANILLA
Underground Mechanical 5/8/2026 Approved JOHN QUINTANILLA
Wood Frame 5/8/2026 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 5/11/2026 Approved JOHN QUINTANILLA
Insulation 5/11/2026 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 5/21/2026 Approved RAUL BARAJAS
Sewer 6/5/2026 Approved JOHN QUINTANILLA
Underground Mechanical 6/5/2026 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 6/11/2026 Approved JOHN QUINTANILLA
HVAC-Rough 6/11/2026 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 6/15/2026 Approved BRENDAN MORELLI
Green Building Rough 6/15/2026 Approved BRENDAN MORELLI
Insulation 6/17/2026 Approved ALEX COLIN
Interior/Exterior Lathing 6/17/2026 Partial Approval ALEX COLIN
Drywall Nailing 6/24/2026 Approved ALEX COLIN