6516 W FIREBRAND ST 90045

Certificate Information: 6516 W FIREBRAND ST 90045

Application / Permit
26014-30000-02022
Plan Check / Job No.
B26WL03356
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-story addition (194 sf) to (e) single story S.F.D. with attached patio cover (126 sf) at rear COMPLY WITH DEPARTMENT ORDER effective date 06/12/2026. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE. CEIS Case Number is 1083655.
Permit Issued
Issued on 6/22/2026
Issuing Office
West Los Angeles
Current Status
Issued on 6/22/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/29/2026 APPLICANT
Assigned to Plan Check Engineer 6/5/2026 REZA HAGHIGHAT
Corrections Issued 6/8/2026 REZA HAGHIGHAT
Building Plans Picked Up 6/9/2026 APPLICANT
Plan Check Approved 6/17/2026 AMY GUEVARRA
Issued 6/22/2026 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/11/2026 JEFF LOREDO
Roof/Waste drainage to street Cleared 6/11/2026 JEFF LOREDO
Sewer availability Cleared 6/11/2026 JEFF LOREDO
Grading Pre-Inspection Cleared 6/15/2026 RUSSELL BONVOULOIR

Contact Information

Contractor Owner-Builder       ,
Engineer Hamilton,, John O; Lic. No.: C53284 11852 FREEMAN AVENUE      HAWTHORNE, CA 90250

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/24/2026 Corrections Issued ANDREW BEELI
Footing/Foundation/Slab 6/24/2026 Not Ready for Inspection ANDREW BEELI
Green Building Rough 6/24/2026 Not Ready for Inspection ANDREW BEELI
METHANE-Barrier 6/24/2026 Not Ready for Inspection ANDREW BEELI
METHANE-Rough 6/24/2026 Not Ready for Inspection ANDREW BEELI
METHANE-Subgrade 6/24/2026 Not Ready for Inspection ANDREW BEELI
Rough-Elec/Plmb/HVAC 6/24/2026 Not Ready for Inspection ANDREW BEELI
Floor/Roof Diaphrgm/Shear Wall 6/26/2026 Corrections Issued ANDREW BEELI
Footing/Foundation/Slab 6/26/2026 Partial Approval ANDREW BEELI
METHANE-Barrier 6/26/2026 Not Ready for Inspection ANDREW BEELI
METHANE-Subgrade 6/26/2026 Not Ready for Inspection ANDREW BEELI
PLUMBING-Rough 6/26/2026 Corrections Issued ANDREW BEELI
Footing/Foundation/Slab 7/1/2026 Not Ready for Inspection ANDREW BEELI
METHANE-Barrier 7/1/2026 Not Ready for Inspection ANDREW BEELI
METHANE-Subgrade 7/1/2026 Not Ready for Inspection ANDREW BEELI
Footing/Foundation/Slab 7/7/2026 Partial Approval ANDREW BEELI
METHANE-Barrier 7/7/2026 Not Ready for Inspection ANDREW BEELI
METHANE-Subgrade 7/7/2026 Not Ready for Inspection ANDREW BEELI
Pre-Inspection 7/9/2026 Approved ANDREW BEELI