10832 1/2 N ODELL AVE 91040
Certificate Information: 10832 1/2 N ODELL AVE 91040
- Application / Permit
- 26014-30000-01370
- Plan Check / Job No.
- B26WL02168
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ROOM ADDITION TO AN (E) SFD. ****ALL WORK PER WFPP
- Permit Issued
- Issued on 5/8/2026
- Issuing Office
- Current Status
- Issued on 5/8/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/14/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2026 | RICHARD GARCIA |
| Corrections Issued | 4/18/2026 | RICHARD GARCIA |
| Building Plans Picked Up | 4/20/2026 | APPLICANT |
| Plan Check Approved | 5/8/2026 | KAVIAN REFAHI |
| Issued | 5/8/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/1/2026 | JEFF LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2026 | JEFF LOREDO |
| Grading Pre-Inspection | Cleared | 5/8/2026 | RICHARD GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/14/2026 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 5/15/2026 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 5/26/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Deputy Drilled-In Anchors | 5/28/2026 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 6/1/2026 | Approved | NICHOLAS TROWBRIDGE |
| Special/Order Compliance | 6/1/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Wood Frame | 6/11/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 6/22/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 6/22/2026 | Approved | NICHOLAS TROWBRIDGE |
| Wood Frame | 6/22/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 6/26/2026 | Corrections Issued | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2026 | Partial Approval | MICHEL ABAJAN |
| Insulation | 7/6/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 7/6/2026 | Partial Approval | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 7/14/2026 | Approved | NICHOLAS TROWBRIDGE |