19044 W HALSTED ST 91324
Certificate Information: 19044 W HALSTED ST 91324
- Application / Permit
- 26014-20000-01241
- Plan Check / Job No.
- B26VN08930
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan 1. NEW ADDITION 187.42 S.F. TOTAL 2. ADD NEW BATH SUITE 3. ADD NEW WALK IN CLOSET 4. NEW PLUMBING FOR THE BATH SUITE 5. NEW LIGHTING FOR THE BATHROOM AND WALK IN CLOSET
- Permit Issued
- Issued on 5/4/2026
- Issuing Office
- Current Status
- Issued on 5/4/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/6/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2026 | SUNMIN LEE |
| Corrections Issued | 4/14/2026 | SUNMIN LEE |
| Applicant returned to address corrections | 4/26/2026 | EDWIN MARTINEZ |
| Applicant returned to address corrections | 4/28/2026 | NEHEMIAS RAMOS |
| Plan Check Approved | 5/4/2026 | NEHEMIAS RAMOS |
| Issued | 5/4/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2026 | AMIR ZEIN |
| Sewer availability | Cleared | 4/23/2026 | AMIR ZEIN |
| Roof/Waste drainage to street | Cleared | 4/30/2026 | DAVID LOPEZ |
Contact Information
| Contractor | Mg All Construction; Lic. No.: 1082580-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Interior/Exterior Lathing | 7/23/2026 |
Inspection Request History
| PLUMBING-Rough | 5/11/2026 | Partial Approval | JEFFREY PARD |
| Deputy Drilled-In Anchors | 5/13/2026 | Conditional Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 5/13/2026 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 6/15/2026 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 6/15/2026 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 6/15/2026 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 6/15/2026 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 6/18/2026 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2026 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 6/18/2026 | Approved | JEFFREY HARTLINE |
| Insulation | 6/26/2026 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 6/26/2026 | Partial Approval | CHRISTOPHER WILSON |
| Drywall Nailing | 7/6/2026 | Approved | IVAN SARABIA |
| Shower Pan | 7/6/2026 | Corrections Issued | IVAN SARABIA |
| Special/Order Compliance | 7/6/2026 | Partial Inspection | CHRISTOPHER WILSON |
| Shower Pan | 7/17/2026 | Approved | IVAN SARABIA |
| Special/Order Compliance | 7/17/2026 | Partial Inspection | CHRISTOPHER WILSON |