13770-13772 W JUDD ST 91331
Certificate Information: 13770-13772 W JUDD ST 91331
- Application / Permit
- 26014-20000-00924
- Plan Check / Job No.
- B26VN06751
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 28' X 32' ADDITION TO (E) SFD INCLUDING (N) 15' X 32' JUNIOR ACCESSORY DWELLING PER GC 66323(a)(1 )and 66333 ADDITION TO (E) SINGLE FAMILY DWELLING ALL WORK PER WFPP
- Permit Issued
- Issued on 5/8/2026
- Issuing Office
- Current Status
- Issued on 5/8/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/12/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2026 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 3/17/2026 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 3/23/2026 | APPLICANT |
| Applicant returned to address corrections | 5/5/2026 | MINA HABILI |
| Issued | 5/8/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2026 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 4/16/2026 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2026 | ROSE STEIN-WENDT |
| Sewer availability | Cleared | 4/17/2026 | ROSE STEIN-WENDT |
| ZI | Cleared | 4/30/2026 | FIPE LEILUA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 5/21/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/21/2026 | Partial Approval | MICHEL ABAJAN |
| Sewer | 5/21/2026 | Approved | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 5/27/2026 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/27/2026 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 5/27/2026 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/24/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/24/2026 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2026 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 6/24/2026 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 6/24/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/24/2026 | Approved | MICHEL ABAJAN |
| Insulation | 6/30/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/30/2026 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 7/13/2026 | Approved | MICHEL ABAJAN |