14982 W VALLEYHEART DR 91403

Certificate Information: 14982 W VALLEYHEART DR 91403

Application / Permit
26014-20000-00738
Plan Check / Job No.
B26VN05349
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) COVERED PORCH AND REPLACE WITH IRREG SHAPED ADDITION TO ENLARGE ENTRY. ADD SKYLIGHTS.
Permit Issued
Issued on 3/24/2026
Issuing Office
Current Status
Issued on 3/24/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/27/2026 APPLICANT
Assigned to Plan Check Engineer 3/5/2026 JEROME MAGAT PALMA
Corrections Issued 3/7/2026 JEROME MAGAT PALMA
Building Plans Picked Up 3/10/2026 APPLICANT
Issued 3/24/2026 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Builders Boulevard Inc; Lic. No.: 1052531-B 6320 TOPANGA CANYON BLVD 1630      WOODLAND HILLS, CA 91367
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/17/2026 Corrections Issued MICHAEL CORTEZ
BUILDING-Rough-Frame 5/12/2026 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 5/12/2026 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/12/2026 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 5/12/2026 Corrections Issued MISAEL ESPARZA
Green Building Rough 5/12/2026 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 5/12/2026 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 5/12/2026 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 5/18/2026 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 5/18/2026 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 5/18/2026 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/18/2026 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 5/18/2026 Partial Approval MISAEL ESPARZA
Green Building Rough 5/18/2026 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 5/18/2026 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 5/18/2026 Approved MISAEL ESPARZA
PLUMBING-Rough 5/18/2026 Not Ready for Inspection MISAEL ESPARZA
Reinforced Concrete Frame 5/18/2026 Partial Inspection MISAEL ESPARZA
Wood Frame 5/18/2026 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 5/21/2026 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/21/2026 Corrections Issued MISAEL ESPARZA
HVAC-Rough 5/21/2026 Approved MISAEL ESPARZA
Interior/Exterior Lathing 5/21/2026 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 5/21/2026 Corrections Issued MISAEL ESPARZA
Deputy Drilled-In Anchors 5/26/2026 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/26/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 5/26/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Insulation 5/28/2026 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 5/28/2026 Partial Approval NICHOLAS TROWBRIDGE
Drywall Nailing 6/2/2026 Approved RAUL OLAGI