8619 N LOUISE AVE 91325

Certificate Information: 8619 N LOUISE AVE 91325

Application / Permit
26014-20000-00625
Plan Check / Job No.
B26VN04591
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
EPLAN. NEW DETACHED POOL EQUIPEMENT STRUCTURE. ALL WORK PER WFPP
Permit Issued
Issued on 3/27/2026
Issuing Office
Current Status
Issued on 3/27/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/20/2026 APPLICANT
Assigned to Plan Check Engineer 2/25/2026 ARAMIK SHAHMIRZAIAN
Corrections Issued 2/26/2026 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 3/10/2026 AUNG SOE
Plan Check Approved 3/10/2026 AUNG SOE
Issued 3/27/2026 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/8/2026 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/8/2026 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/9/2026 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 6/10/2026 Corrections Issued CHRISTOPHER ROJAS
Equipment Noise Level 6/15/2026 Approved AGUSTIN ALVAREZMORALES
BUILDING-Rough-Frame 6/25/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Final 6/25/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 6/25/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 6/25/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 6/25/2026 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 6/25/2026 SGSOV Not Ready CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/7/2026 Corrections Issued KEVIN BERBERYAN