18308-18310 W GRESHAM ST 91325

Certificate Information: 18308-18310 W GRESHAM ST 91325

Application / Permit
26014-20000-00543
Plan Check / Job No.
B26VN03984
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) SFD, CONVERT PORTION OF SFD W/ ADDITION INTO A ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (e) AND CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) and 66333 AND REROOF THE (E) SFD. ALL WORK PER WFPP.
Permit Issued
Issued on 3/6/2026
Issuing Office
Valley
Current Status
Issued on 3/6/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/13/2026 APPLICANT
Assigned to Plan Check Engineer 2/20/2026 ARTIN ZARUKIAN
Corrections Issued 2/21/2026 ARTIN ZARUKIAN
Building Plans Picked Up 2/24/2026 APPLICANT
Issued 3/6/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/4/2026 STEVE MELGAR
Roof/Waste drainage to street Cleared 3/4/2026 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 3/5/2026 STEVE MELGAR
Sewer availability Cleared 3/5/2026 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/12/2026 Partial Approval DAVID SCANTLIN
Deputy Drilled-In Anchors 3/13/2026 Conditional Approval DAVID SCANTLIN
Footing/Foundation/Slab 3/16/2026 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 3/16/2026 Not Ready for Inspection DAVID SCANTLIN
Footing/Foundation/Slab 3/17/2026 Approved DAVID SCANTLIN
PLUMBING-Rough 3/17/2026 Partial Approval DAVID SCANTLIN
Insulation 3/25/2026 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 3/25/2026 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 3/27/2026 Partial Approval JACK KARGODORIAN
Green Building Rough 3/27/2026 Partial Approval JACK KARGODORIAN
Insulation 3/27/2026 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 3/27/2026 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 4/9/2026 Partial Approval DAVID SCANTLIN
Green Building Rough 4/9/2026 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 4/9/2026 Not Ready for Inspection DAVID SCANTLIN
Shower Pan 4/9/2026 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 4/24/2026 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 4/24/2026 Approved DAVID SCANTLIN
Green Building Rough 4/24/2026 Approved DAVID SCANTLIN
Interior/Exterior Lathing 4/24/2026 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 4/24/2026 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 4/27/2026 Approved DAVID SCANTLIN
HVAC-Rough 4/27/2026 Approved DAVID SCANTLIN
PLUMBING-Rough 4/27/2026 Approved DAVID SCANTLIN
Insulation 4/29/2026 Approved DAVID SCANTLIN
Drywall Nailing 5/4/2026 Approved ARUTYUN MADATYAN
Insulation 5/4/2026 Approved ARUTYUN MADATYAN