9444-9446 N URBANA AVE 91331

Certificate Information: 9444-9446 N URBANA AVE 91331

Application / Permit
26014-20000-00539
Plan Check / Job No.
B26VN03962
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) REAR PATIO, CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) and 66333 AND 27'-5" X 13'-7" (PATIO) & 3'-4" X 6'-11" ADDITION TO (E) SFD.
Permit Issued
Issued on 3/19/2026
Issuing Office
Current Status
CofO Issued on 6/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2026 APPLICANT
Assigned to Plan Check Engineer 2/18/2026 ARTIN ZARUKIAN
Corrections Issued 2/18/2026 ARTIN ZARUKIAN
Building Plans Picked Up 2/20/2026 APPLICANT
Applicant returned to address corrections 3/19/2026 ARAMIK SHAHMIRZAIAN
Plan Check Approved 3/19/2026 NAREG ATARIAN
Issued 3/19/2026 APPLICANT
CofO in Progress 5/28/2026 OGANES TARAKHCHYAN
Permit Finaled 6/11/2026 RUBEN SALAS
CofO Issued 6/11/2026 RUBEN SALAS
Permit Finaled 6/11/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/23/2026 TONY CHIANG
Eng Process Fee Ord 176,300 Cleared 2/23/2026 TONY CHIANG
Roof/Waste drainage to street Cleared 2/23/2026 TONY CHIANG
Sewer availability Cleared 2/23/2026 TONY CHIANG

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/25/2026 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 4/6/2026 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/14/2026 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/14/2026 Approved OGANES TARAKHCHYAN
Green Building Rough 4/14/2026 Approved OGANES TARAKHCHYAN
HVAC-Rough 4/14/2026 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 4/14/2026 Approved OGANES TARAKHCHYAN
Insulation 4/29/2026 Approved OGANES TARAKHCHYAN
Drywall Nailing 4/30/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/30/2026 Partial Approval OGANES TARAKHCHYAN
Final 5/26/2026 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 5/26/2026 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/26/2026 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 5/26/2026 Approved OGANES TARAKHCHYAN