7030 N BEVIS AVE 91405
Certificate Information: 7030 N BEVIS AVE 91405
- Application / Permit
- 26014-20000-00537
- Plan Check / Job No.
- B26VN03922
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED FAMILY RM, HALLWAY, BATHRM & 2 BEDRM ADDITION AT REAR TO EX 1-STORY SFD. ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/19/2026
- Issuing Office
- Valley
- Current Status
- Issued on 2/19/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/12/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 2/12/2026 | HAYATO TSUCHIYA |
| Corrections Issued | 2/12/2026 | HAYATO TSUCHIYA |
| Plan Check Approved | 2/19/2026 | ANGELICA DAVE |
| Issued | 2/19/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2026 | JESUS CISNEROS |
| Roof/Waste drainage to street | Cleared | 2/17/2026 | JESUS CISNEROS |
| Sewer availability | Cleared | 2/17/2026 | JESUS CISNEROS |
Contact Information
| Contractor | Markarian Setrag; Lic. No.: 832632-B | 3975 CAMINO DE LA PLAZA SAN YSIDRO, CA 92173 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/10/2026 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 3/11/2026 | Conditional Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 3/24/2026 | Partial Approval | VINCENT HANLEY |
| Insulation | 3/24/2026 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 3/24/2026 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2026 | Partial Approval | VINCENT HANLEY |
| Insulation | 4/1/2026 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 4/1/2026 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2026 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/18/2026 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2026 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/18/2026 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 5/18/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/18/2026 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/26/2026 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/26/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/26/2026 | Partial Approval | VINCENT HANLEY |
| Insulation | 5/28/2026 | Approved | VINCENT HANLEY |
| Drywall Nailing | 6/3/2026 | Approved | VINCENT HANLEY |