13139-13139 1/2 W EUSTACE ST 91331
Certificate Information: 13139-13139 1/2 W EUSTACE ST 91331
- Application / Permit
- 26014-20000-00452
- Plan Check / Job No.
- B26VN03397
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan-NEW ATTACHED JUNIOR ACCESSORY DWELLING UNIT TO EXISTING SINGLE FAMILY DWELLING UNIT PER GC 66323(a)(1) and 66333. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/30/2026
- Issuing Office
- Current Status
- Issued on 3/30/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/7/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2026 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 2/12/2026 | ARAMIK SHAHMIRZAIAN |
| Applicant returned to address corrections | 3/18/2026 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 3/28/2026 | ARAMIK SHAHMIRZAIAN |
| Issued | 3/30/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2026 | JESUS CISNEROS |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2026 | JESUS CISNEROS |
| Roof/Waste drainage to street | Cleared | 2/24/2026 | JESUS CISNEROS |
| Sewer availability | Cleared | 2/24/2026 | JESUS CISNEROS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lambert,, Will A; Lic. No.: S5430 | 223 E THOUSAND OAKS BLVD304 THOUSAND OAKS, CA 91360 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/2/2026 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 4/3/2026 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/3/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/3/2026 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2026 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/12/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/12/2026 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2026 | Partial Approval | MICHEL ABAJAN |
| Gas Test | 5/12/2026 | Approved | MICHEL ABAJAN |
| Green Building Rough | 5/12/2026 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 5/12/2026 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 5/12/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/12/2026 | Approved | MICHEL ABAJAN |
| Insulation | 5/15/2026 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/15/2026 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 5/19/2026 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/29/2026 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 5/29/2026 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 6/22/2026 | Approved | MICHEL ABAJAN |
| Final | 6/22/2026 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 6/22/2026 | Approved | MICHEL ABAJAN |
| HVAC-Final | 6/22/2026 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 6/22/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 6/22/2026 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/22/2026 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 6/22/2026 | Approved | MICHEL ABAJAN |