7769 N FULTON AVE 91605
Certificate Information: 7769 N FULTON AVE 91605
- Application / Permit
- 26014-20000-00403
- Plan Check / Job No.
- B26VN03072
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL & ADDITION TO MAKE A 80'8"X57'7" 1-STORY SINGLE FAMILY DWELLING WITH AN ATTACHED 2-CAR GARAGE AND PATIO. (NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT)
- Permit Issued
- Issued on 3/19/2026
- Issuing Office
- Current Status
- Issued on 3/19/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/4/2026 | APPLICANT |
| Assigned to Zoning Architect | 2/5/2026 | LINGHUI YU |
| Assigned to Plan Check Engineer | 2/12/2026 | MARVEL DELACRUZ |
| Corrections Issued | 2/19/2026 | MARVEL DELACRUZ |
| Quality Review Completed | 2/20/2026 | STEVEN KIM |
| Building Plans Picked Up | 2/23/2026 | APPLICANT |
| Applicant returned to address corrections | 3/13/2026 | MARVEL DELACRUZ |
| Plan Check Approved | 3/19/2026 | MARVEL DELACRUZ |
| Issued | 3/19/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2026 | JESUS CISNEROS |
| Sewer availability | Cleared | 2/24/2026 | JESUS CISNEROS |
| Roof/Waste drainage to street | Cleared | 3/6/2026 | LEE GUILBEAUX |
| Zoning Plan Check | Cleared | 3/10/2026 | LINGHUI YU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/20/2026 | Approved | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 3/23/2026 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 3/23/2026 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/26/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 3/26/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2026 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/28/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 5/7/2026 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/7/2026 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/12/2026 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/12/2026 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 5/12/2026 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 5/12/2026 | Approved | OGANES TARAKHCHYAN |
| Insulation | 5/13/2026 | Approved | OGANES TARAKHCHYAN |
| Insulation | 5/15/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/15/2026 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 5/15/2026 | Approved | OGANES TARAKHCHYAN |