4467 N WOODLEY AVE 91436

Certificate Information: 4467 N WOODLEY AVE 91436

Application / Permit
26014-20000-00388
Plan Check / Job No.
B26VN02969
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED PATIO COVER ADDITION W/ ROOF TOP DECK TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/15/2026
Issuing Office
Current Status
Issued on 6/15/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/3/2026 APPLICANT
Assigned to Zoning Architect 2/12/2026 MELISSA QUINONES
Assigned to Plan Check Engineer 2/19/2026 RAPHAEL ROSAS
Corrections Issued 2/26/2026 RAPHAEL ROSAS
Quality Review Completed 3/2/2026 STEVEN KIM
Building Plans Picked Up 3/3/2026 APPLICANT
Applicant returned to address corrections 6/4/2026 RAPHAEL ROSAS
Plan Check Approved 6/15/2026 RAPHAEL ROSAS
Issued 6/15/2026 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 3/11/2026 JASON CHAN
Miscellaneous Cleared 3/11/2026 JASON CHAN
Miscellaneous Cleared 3/11/2026 JASON CHAN
Miscellaneous Cleared 3/11/2026 JASON CHAN
Roof/Waste drainage to street Cleared 3/15/2026 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/15/2026 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/8/2026 LEE GUILBEAUX
Distance to fire station Cleared 4/13/2026 JERRY KAO
Hydrant and Access approval Cleared 4/13/2026 JERRY KAO
Zoning Plan Check Cleared 5/20/2026 RAPHAEL ROSAS
GPI Written Notices Cleared 6/4/2026 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 6/4/2026 RAPHAEL ROSAS

Contact Information

Contractor Gruen Construction Co Inc; Lic. No.: 746376-B PO BOX 516      NEWBURY PARK, CA 91319
Engineer Kile,, Johnny C; Lic. No.: C92658 4077 GLENALBYN DRIVE      LOS ANGELES, CA 90065

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Deputy Reinf. Concrete 7/24/2026   

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/25/2026 Not Ready for Inspection THOMAS FINNILA
Pre-Inspection 6/25/2026 Partial Inspection THOMAS FINNILA
Footing/Foundation/Slab 6/30/2026 Approved IVAN SARABIA
Special/Order Compliance 6/30/2026 Partial Inspection SEAN WIRCH