16300 W CHASE ST 91343
Certificate Information: 16300 W CHASE ST 91343
- Application / Permit
- 26014-20000-00364
- Plan Check / Job No.
- B26VN02792
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- 14'-0"X17'-6"ADDITION TO THE (E) ALQ.
- Permit Issued
- Issued on 2/5/2026
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 4/24/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/2/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2026 | JESSE ARELLANO |
| Corrections Issued | 2/2/2026 | JESSE ARELLANO |
| Plan Check Approved | 2/5/2026 | NAREG ATARIAN |
| Issued | 2/5/2026 | APPLICANT |
| CofO in Progress | 4/24/2026 | KIRK SANDERS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2026 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 2/4/2026 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/4/2026 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/2/2026 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 3/6/2026 | Conditional Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/17/2026 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 3/17/2026 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2026 | Approved | KIRK SANDERS |
| Green Building Rough | 3/17/2026 | Not Ready for Inspection | KIRK SANDERS |
| Interior/Exterior Lathing | 3/19/2026 | Approved | JOSE AVILA |
| Insulation | 3/23/2026 | Approved | KIRK SANDERS |
| Drywall Nailing | 3/25/2026 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 4/10/2026 | Approved | WAYNE REGESTER |
| Final | 4/10/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Footing/Foundation/Slab | 4/10/2026 | Approved | WAYNE REGESTER |
| Green Building Final | 4/10/2026 | Corrections Issued | WAYNE REGESTER |
| Green Building Rough | 4/10/2026 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 4/10/2026 | SGSOV Approved | WAYNE REGESTER |
| Smoke Detectors | 4/10/2026 | Approved | WAYNE REGESTER |
| Final | 4/23/2026 | OK to Issue CofO | KIRK SANDERS |
| Green Building Final | 4/23/2026 | Approved | KIRK SANDERS |