6051 N COLFAX AVE 91606

Certificate Information: 6051 N COLFAX AVE 91606

Application / Permit
26014-20000-00363
Plan Check / Job No.
B26VN02787
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED REC ROOM ADDITION ATTACHED TO EXISTING DETACHED ADU.
Permit Issued
Issued on 4/17/2026
Issuing Office
Current Status
CofO in Progress on 7/8/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/2/2026 APPLICANT
Assigned to Plan Check Engineer 2/4/2026 SERGIO MUNIZ
Corrections Issued 2/5/2026 SERGIO MUNIZ
Applicant returned to address corrections 3/12/2026 SERGIO MUNIZ
Applicant returned to address corrections 3/27/2026 SERGIO MUNIZ
Applicant returned to address corrections 4/4/2026 SERGIO MUNIZ
Plan Check Approved 4/14/2026 SERGIO MUNIZ
Issued 4/17/2026 APPLICANT
CofO in Progress 7/8/2026 ROBERTO PALACIOS-LOPEZ

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/19/2026 ARMEN MEHRABIAN
Eng Process Fee Ord 176,300 Cleared 2/25/2026 ARMEN MEHRABIAN
Miscellaneous Cleared 4/8/2026 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/12/2026 Conditional Approval GAREN HAYRAPETYAN
Footing/Foundation/Slab 5/15/2026 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 5/26/2026 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Gas Test 5/26/2026 No Access for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/29/2026 Conditional Approval ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 5/29/2026 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 5/29/2026 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/2/2026 Corrections Issued GAREN HAYRAPETYAN
ELECTRICAL-Rough 6/2/2026 Approved GAREN HAYRAPETYAN
Gas Test 6/2/2026 Approved GAREN HAYRAPETYAN
Green Building Rough 6/2/2026 Approved GAREN HAYRAPETYAN
HVAC-Rough 6/2/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 6/2/2026 Approved GAREN HAYRAPETYAN
Insulation 6/3/2026 Conditional Approval GAREN HAYRAPETYAN
Interior/Exterior Lathing 6/3/2026 Partial Approval GAREN HAYRAPETYAN
Drywall Nailing 6/8/2026 Approved GAREN HAYRAPETYAN
Special/Order Compliance 6/8/2026 Corrections Issued GAREN HAYRAPETYAN
BUILDING-Rough-Frame 6/26/2026 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 6/26/2026 Approved GAREN HAYRAPETYAN
Final 6/26/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 6/26/2026 Approved GAREN HAYRAPETYAN
HVAC-Final 6/26/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Final 6/26/2026 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 6/26/2026 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 6/26/2026 Approved GAREN HAYRAPETYAN
Final 7/7/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ