3470 S GRAND VIEW BLVD 90066

Certificate Information: 3470 S GRAND VIEW BLVD 90066

Application / Permit
26014-20000-00304
Plan Check / Job No.
B26VN02274
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) 1243 SF SFD EXCEPT FOR 3'-11" OF WALL AND FOUNDATION TO REMAIN. REBUILD iRREGULAR SHAPED 2-STORY SFD W/ 2-CAR GARAGE AND TRELLIS PATIO COVER AND ROOFTOP DECK. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/27/2026
Issuing Office
Current Status
Issued on 5/27/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/27/2026 APPLICANT
Assigned to Zoning Architect 1/30/2026 NICOLE SALEEBA
Assigned to Plan Check Engineer 2/5/2026 RAPHAEL ROSAS
Corrections Issued 2/10/2026 RAPHAEL ROSAS
Quality Review Completed 2/12/2026 STEVEN KIM
Building Plans Picked Up 2/12/2026 APPLICANT
Plan Check Approved 5/27/2026 RAPHAEL ROSAS
Issued 5/27/2026 APPLICANT

Permit Application Clearance Information

CPC Cleared 2/19/2026 DAVID URITA
CPC Cleared 2/19/2026 DAVID URITA
Eng Process Fee Ord 176,300 Cleared 2/19/2026 TONY CHIANG
Sewer availability Cleared 2/19/2026 TONY CHIANG
Low Impact Development (LID) Cleared 3/6/2026 ERNEST TSE
Roof/Waste drainage to street Cleared 3/12/2026 JEREMY CHOK
Specific Plan Cleared 3/26/2026 PEDRO AYALA
Zoning Plan Check Cleared 4/28/2026 NICOLE SALEEBA
GPI Written Notices Cleared 5/15/2026 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 5/15/2026 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/29/2026 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 5/29/2026 Partial Inspection ANTHONY EGSON
Deputy Drilled-In Anchors 6/4/2026 Conditional Approval BOBBY KEY
Deputy Other (see comments) 6/4/2026 Conditional Approval BOBBY KEY
Deputy Steel/Welding 6/4/2026 Conditional Approval KIRK SANDERS
Footing/Foundation/Slab 6/4/2026 Conditional Approval KIRK SANDERS
Special/Order Compliance 6/4/2026 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 7/1/2026 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 7/1/2026 Approved KIRK SANDERS
PLUMBING-Rough 7/1/2026 Partial Approval KIRK SANDERS
Sewer 7/1/2026 Approved KIRK SANDERS
Insulation 7/6/2026 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 7/8/2026 Partial Approval MICHAEL LEWIS
Deputy Steel/Welding 7/14/2026 Conditional Approval KIRK SANDERS
Structural Steel Frame 7/14/2026 Partial Approval MORRIS JACKSON