13511 W JUDD ST 91331

Certificate Information: 13511 W JUDD ST 91331

Application / Permit
26014-20000-00274
Plan Check / Job No.
B26VN02045
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SECOND STORY ADDITION WITH MAJOR REMODEL AND CONVERSION OF EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 663323(a)(1)
Permit Issued
Issued on 7/8/2026
Issuing Office
Current Status
Issued on 7/8/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/26/2026 APPLICANT
Assigned to Plan Check Engineer 1/29/2026 DANIEL ABRAMYAN
Assigned to Zoning Architect 1/30/2026 MANUEL ZAVALETA
Corrections Issued 1/31/2026 DANIEL ABRAMYAN
Quality Review Completed 2/6/2026 OMID HEDAYAT
Applicant returned to address corrections 5/28/2026 DANIEL ABRAMYAN
Applicant returned to address corrections 6/30/2026 DANIEL ABRAMYAN
Plan Check Approved 7/7/2026 DANIEL ABRAMYAN
Issued 7/8/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/6/2026 JEFF LOREDO
Roof/Waste drainage to street Cleared 2/6/2026 JEFF LOREDO
Eng Process Fee Ord 176,300 Cleared 2/17/2026 JEFF LOREDO
Sewer availability Cleared 2/17/2026 JEFF LOREDO
Zoning Plan Check Cleared 7/6/2026 Daniel San Juan

Contact Information

Contractor Fehu Home Improvement Llc; Lic. No.: 1107500-B       ,
Engineer Santos,, Michael; Lic. No.: C77657 16202 ORION AVE      CHINO, CA 91708

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Excavation/Setback/Form/Re-Bar 7/22/2026    Time Frame: 1-3
METHANE-Subgrade 7/22/2026    Time Frame: 1-3
METHANE-Barrier 7/22/2026    Time Frame: 1-3
Footing/Foundation/Slab 7/22/2026    Time Frame: 1-3

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/14/2026 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 7/14/2026 Partial Inspection MICHEL ABAJAN
METHANE-Barrier 7/14/2026 Not Ready for Inspection MICHEL ABAJAN
METHANE-Subgrade 7/14/2026 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 7/14/2026 Partial Inspection MICHEL ABAJAN
METHANE-Subgrade 7/21/2026 Approved MICHEL ABAJAN
PLUMBING-Rough 7/21/2026 Partial Approval MICHEL ABAJAN