2656 S HOBART BLVD 90018
Certificate Information: 2656 S HOBART BLVD 90018
- Application / Permit
- 26014-20000-00254
- Plan Check / Job No.
- B26VN01920
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING ATTIC SPACE INTO A SECOND STORY FOR THE EXISTING SINGLE FAMILY DWELLING. NO CHANGE TO THE BUILDING ROOF.
- Permit Issued
- Issued on 4/15/2026
- Issuing Office
- Metro
- Current Status
- Issued on 4/15/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/23/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2026 | VAHAN JIVALAGIAN |
| Assigned to Zoning Architect | 1/30/2026 | NICOLE SALEEBA |
| Corrections Issued | 2/1/2026 | VAHAN JIVALAGIAN |
| Quality Review Completed | 2/3/2026 | OMID HEDAYAT |
| Building Plans Picked Up | 2/4/2026 | APPLICANT |
| Applicant returned to address corrections | 3/23/2026 | VAHAN JIVALAGIAN |
| Plan Check Approved | 4/15/2026 | VAHAN JIVALAGIAN |
| Issued | 4/15/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/17/2026 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2026 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/18/2026 | CARLOS AGUILERA |
| Zoning Plan Check | Cleared | 3/11/2026 | NICOLE SALEEBA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/5/2026 | Partial Approval | OSVALDO PARAMO |
| METHANE-Barrier | 5/5/2026 | Approved | OSVALDO PARAMO |
| METHANE-Subgrade | 5/5/2026 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/23/2026 | Approved | WILLIAM SIERRA |
| PLUMBING-Rough | 6/23/2026 | Approved | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 6/25/2026 | Corrections Issued | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2026 | Corrections Issued | WILLIAM SIERRA |
| Green Building Rough | 6/25/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| METHANE-Rough | 6/25/2026 | Approved | WILLIAM SIERRA |
| Deputy Drilled-In Anchors | 6/26/2026 | Conditional Approval | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 6/26/2026 | Conditional Approval | ALIZAH MAYAGOITIA |
| HVAC-Rough | 7/6/2026 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/8/2026 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2026 | Approved | WILLIAM SIERRA |
| Green Building Rough | 7/8/2026 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 7/8/2026 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 7/8/2026 | Partial Approval | WILLIAM SIERRA |
| Insulation | 7/13/2026 | Approved | WILLIAM SIERRA |