6051 N COLFAX AVE 91606
Certificate Information: 6051 N COLFAX AVE 91606
- Application / Permit
- 26014-20000-00194
- Plan Check / Job No.
- B26VN01406
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. 1-story addition to (e) SFD ; work per WFPP
- Permit Issued
- Issued on 2/8/2026
- Issuing Office
- Current Status
- Issued on 2/8/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/20/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2026 | REZA HAGHIGHAT |
| Corrections Issued | 1/21/2026 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 1/29/2026 | REZA HAGHIGHAT |
| Plan Check Approved | 2/3/2026 | REZA HAGHIGHAT |
| Issued | 2/8/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/1/2026 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/1/2026 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/1/2026 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2026 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/27/2026 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2026 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 3/10/2026 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 3/10/2026 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 3/10/2026 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 3/10/2026 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 3/10/2026 | Approved | GAREN HAYRAPETYAN |
| Insulation | 3/12/2026 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 3/16/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 3/26/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 3/26/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 3/26/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 5/13/2026 | Conditional Approval | GAREN HAYRAPETYAN |
| Green Building Final | 5/13/2026 | Approved | GAREN HAYRAPETYAN |