11948 N CLONLEE AVE 91344

Certificate Information: 11948 N CLONLEE AVE 91344

Application / Permit
26014-20000-00152
Plan Check / Job No.
B26VN01091
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN . ADDITION TO EXISTING SINGLE FAMILY HOUSE.
Permit Issued
Issued on 4/17/2026
Issuing Office
Current Status
Issued on 4/17/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/16/2026 APPLICANT
Assigned to Zoning Architect 1/22/2026 CAMERON JONES
Assigned to Plan Check Engineer 1/29/2026 ARSALAN SHABESTARI
Corrections Issued 2/10/2026 ARSALAN SHABESTARI
Quality Review Completed 2/24/2026 CHAD DOI
Plan Check Approved 4/14/2026 ARSALAN SHABESTARI
Plan Check Approved 4/16/2026 INTERNET PERMIT
Issued 4/17/2026 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/12/2026 JESUS CISNEROS
BHO/Hillside ordinance Cleared 2/12/2026 JESUS CISNEROS
BHO/Hillside ordinance Cleared 2/12/2026 JESUS CISNEROS
BHO/Hillside ordinance Cleared 2/12/2026 JESUS CISNEROS
BHO/Hillside ordinance Cleared 2/12/2026 JESUS CISNEROS
Grading Pre-Inspection Cleared 2/25/2026 ALEXANDER HELFER
Eng Process Fee Ord 176,300 Cleared 2/26/2026 MICHAEL BROWN
Hydrant and Access approval Cleared 2/26/2026 KURT CORRAL
Sewer availability Cleared 2/26/2026 MICHAEL BROWN
Roof/Waste drainage to street Cleared 3/4/2026 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 3/4/2026 LEE GUILBEAUX
Zoning Plan Check Cleared 3/12/2026 CAMERON JONES
GPI Written Notices Cleared 4/14/2026 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/24/2026 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/24/2026 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 4/24/2026 Partial Approval CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 4/28/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 4/28/2026 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/12/2026 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/12/2026 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 6/12/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 6/12/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/17/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 6/17/2026 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 6/17/2026 Approved CHRISTOPHER ROJAS
Wood Frame 6/17/2026 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/26/2026 Approved CHRISTOPHER ROJAS
Insulation 6/26/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/26/2026 Partial Approval CHRISTOPHER ROJAS
Shower Pan 7/9/2026 Approved CHRISTOPHER ROJAS