13448 N AZORES AVE 91342
Certificate Information: 13448 N AZORES AVE 91342
- Application / Permit
- 26014-20000-00070
- Plan Check / Job No.
- B26VN00338
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: ALUMINUM PATIO COVER ADDITION TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 2/4/2026
- Issuing Office
- Current Status
- CofO Issued on 3/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2026 | JOSE VELAZQUEZ |
| Corrections Issued | 1/15/2026 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 1/29/2026 | ADAM HEGAZI |
| Plan Check Approved | 2/4/2026 | DANIEL YIP |
| Issued | 2/4/2026 | APPLICANT |
| CofO in Progress | 3/3/2026 | KEVIN BERBERYAN |
| Permit Finaled | 3/13/2026 | RUBEN SALAS |
| CofO Issued | 3/13/2026 | RUBEN SALAS |
| Permit Finaled | 3/13/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2026 | ARMEN MEHRABIAN |
| Roof/Waste drainage to street | Cleared | 1/30/2026 | ARMEN MEHRABIAN |
| ZA Case | Cleared | 1/30/2026 | ASHLEY MACIAS |
| ZA Case | Cleared | 1/30/2026 | ASHLEY MACIAS |
| ZA Case | Cleared | 1/30/2026 | ASHLEY MACIAS |
| ZA Case | Cleared | 1/30/2026 | ASHLEY MACIAS |
| ZA Case | Cleared | 1/30/2026 | ASHLEY MACIAS |
| ZA Case | Cleared | 1/30/2026 | ASHLEY MACIAS |
Contact Information
| Contractor | Bell Remodeling And Construction; Lic. No.: 1039324-B | , |
| Engineer | Putnam,, Carl Matthew; Lic. No.: C68139 | 3441 IVYLINK PL LYNCHBURG, VA 24503 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/18/2026 | Partial Approval | KEVIN BERBERYAN |
| Green Building Rough | 2/18/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 2/23/2026 | Approved | KEVIN BERBERYAN |
| Final | 2/23/2026 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 2/23/2026 | Approved | KEVIN BERBERYAN |
| Green Building Final | 2/23/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Rough | 2/23/2026 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 2/23/2026 | Approved | KEVIN BERBERYAN |
| Final | 3/3/2026 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 3/3/2026 | Approved | KEVIN BERBERYAN |