821 N CHESTNUT AVE 90042

Certificate Information: 821 N CHESTNUT AVE 90042

Application / Permit
26014-10000-01038
Plan Check / Job No.
B26LA10898
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and remodel to a kitchen in a single family dwelling.
Permit Issued
Issued on 4/10/2026
Issuing Office
Valley
Current Status
CofO Issued on 7/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2026 APPLICANT
Assigned to Plan Check Engineer 3/20/2026 JOSE VELAZQUEZ
Corrections Issued 3/20/2026 JOSE VELAZQUEZ
Plan Check Approved 3/31/2026 DANIEL SMILEY
Issued 4/10/2026 APPLICANT
CofO in Progress 7/13/2026 NICHOLAS LOPEZ
Permit Finaled 7/16/2026 DEROLD HAUFF
CofO Issued 7/16/2026 DEROLD HAUFF
Permit Finaled 7/16/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/27/2026 JEFF LOREDO
Eng Process Fee Ord 176,300 Cleared 3/31/2026 CELINA MORENO
Grading Pre-Inspection Cleared 3/31/2026 DANIEL SMILEY

Contact Information

Contractor Landa Builders Inc; Lic. No.: 1138543-B 534 N MANSFIELD AVE      LOS ANGELES, CA 90036
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/22/2026 Corrections Issued DAVID WILLIAMS
BUILDING-Rough-Frame 5/18/2026 Conditional Approval NICHOLAS LOPEZ
ELECTRICAL-Rough 5/18/2026 Approved NICHOLAS LOPEZ
Green Building Rough 5/18/2026 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Rough 5/18/2026 Approved NICHOLAS LOPEZ
MERV13>=Rough 5/18/2026 Approved NICHOLAS LOPEZ
PLUMBING-Rough 5/18/2026 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 5/21/2026 Approved DAVID WILLIAMS
PLUMBING-Rough 5/21/2026 Approved DAVID WILLIAMS
Insulation 5/26/2026 Approved DAVID WILLIAMS
Drywall Nailing 5/29/2026 Approved GEM DE OCAMPO
BUILDING-Rough-Frame 7/2/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 7/2/2026 Corrections Issued NICHOLAS LOPEZ
Final 7/2/2026 Corrections Issued NICHOLAS LOPEZ
Footing/Foundation/Slab 7/2/2026 Approved NICHOLAS LOPEZ
Green Building Final 7/2/2026 Approved NICHOLAS LOPEZ
Green Building Rough 7/2/2026 Approved NICHOLAS LOPEZ
MERV13>=Final 7/2/2026 Approved NICHOLAS LOPEZ
PLUMBING-Final 7/2/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 7/2/2026 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 7/2/2026 Corrections Issued NICHOLAS LOPEZ
ELECTRICAL-Final 7/9/2026 Approved NICHOLAS LOPEZ
Final 7/9/2026 OK to Issue CofO NICHOLAS LOPEZ
PLUMBING-Final 7/9/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 7/9/2026 SGSOV Approved NICHOLAS LOPEZ
Smoke Detectors 7/9/2026 Approved NICHOLAS LOPEZ