917-919 S SYCAMORE AVE 90036

Certificate Information: 917-919 S SYCAMORE AVE 90036

Application / Permit
26014-10000-00860
Plan Check / Job No.
B26LA09065
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ADDITION AND CONVERSTION OF EXISTING LIVING SPACE INTO ADU (ADDRESS #: 917-1/2) IN EXISTING DUPLEX BUILDING PER ENGINEER DESIGN (OrdinanceADU, AttachedADU, LAMC12.22A.33(c) and(e))
Permit Issued
Issued on 3/20/2026
Issuing Office
Metro
Current Status
Issued on 3/20/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/10/2026 APPLICANT
Assigned to Plan Check Engineer 3/13/2026 AUNG SOE
Corrections Issued 3/16/2026 AUNG SOE
Building Plans Picked Up 3/17/2026 APPLICANT
Plan Check Approved 3/20/2026 YILE TIAN
Issued 3/20/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/17/2026 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 3/17/2026 DERRICK MAGEE
Roof/Waste drainage to street Cleared 3/17/2026 DERRICK MAGEE
Sewer availability Cleared 3/17/2026 DERRICK MAGEE
Tenant Habitability Plan Cleared 3/17/2026 HUGO GARRIDO GARZA
CPC Cleared 3/19/2026 GEORGIA SMITH

Contact Information

Contractor Owner-Builder       ,
Engineer Tuna,, Suleyman; Lic. No.: C73294 1044 S MANSFIELD AVE.      LOS ANGELES, CA 90019

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/24/2026 Corrections Issued RONNIE MINDANAO
Shower Pan 3/24/2026 Approved RONNIE MINDANAO
Special/Order Compliance 3/24/2026 Corrections Issued RONNIE MINDANAO
PLUMBING-Rough 3/25/2026 Approved RONNIE MINDANAO
Interior/Exterior Lathing 4/7/2026 Approved RONNIE MINDANAO
Footing/Foundation/Slab 4/20/2026 Approved RONNIE MINDANAO
METHANE-Barrier 4/20/2026 Approved RONNIE MINDANAO
METHANE-Subgrade 4/20/2026 Approved RONNIE MINDANAO
PLUMBING-Rough 4/20/2026 Partial Approval RONNIE MINDANAO
ELECTRICAL-Rough 4/22/2026 Corrections Issued RONNIE MINDANAO
ELECTRICAL-Rough 4/29/2026 Partial Approval RONNIE MINDANAO
Interior/Exterior Lathing 4/29/2026 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Rough 4/29/2026 Not Ready for Inspection RONNIE MINDANAO
Shower Pan 4/29/2026 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 5/7/2026 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 5/7/2026 Partial Approval RONNIE MINDANAO
PLUMBING-Rough 5/7/2026 Approved RONNIE MINDANAO
Shower Pan 5/7/2026 Partial Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 5/12/2026 Partial Approval RONNIE MINDANAO
Insulation 5/12/2026 Partial Approval RONNIE MINDANAO
Interior/Exterior Lathing 5/13/2026 Partial Approval RONNIE MINDANAO
HVAC-Rough 5/15/2026 Partial Approval RONNIE MINDANAO
BUILDING-Rough-Frame 5/29/2026 Not Ready for Inspection RONNIE MINDANAO
Green Building Rough 5/29/2026 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 5/29/2026 Approved RONNIE MINDANAO
METHANE-Rough 5/29/2026 Approved RONNIE MINDANAO
Pre-Inspection 6/1/2026 Approved ENRIQUE MIRELES
Insulation 6/3/2026 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 6/5/2026 Approved Pending GreenApproval RONNIE MINDANAO
Green Building Rough 6/5/2026 Not Ready for Inspection RONNIE MINDANAO
Drywall Nailing 6/8/2026 Partial Approval RONNIE MINDANAO
Drywall Nailing 6/9/2026 Partial Approval ALEX COLIN
Drywall Nailing 6/11/2026 Approved RONNIE MINDANAO
Interior/Exterior Lathing 6/11/2026 Approved RONNIE MINDANAO
Drywall Nailing 6/12/2026 Approved RONNIE MINDANAO