1135 N RAVOLI DR 90272
Certificate Information: 1135 N RAVOLI DR 90272
- Application / Permit
- 26014-10000-00579
- Plan Check / Job No.
- B26LA05839
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. Remodel and addition to (E) Single Family Dwelling w/ attached garage
- Permit Issued
- Issued on 3/4/2026
- Issuing Office
- Current Status
- CofO in Progress on 6/4/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/17/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2026 | AMY GUEVARRA |
| Corrections Issued | 2/23/2026 | AMY GUEVARRA |
| Plan Check Approved | 3/4/2026 | AMY GUEVARRA |
| Issued | 3/4/2026 | APPLICANT |
| CofO in Progress | 6/4/2026 | KEVIN SARGSYAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/26/2026 | LANNY MERRICK |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2026 | TONY CHIANG |
| Roof/Waste drainage to street | Cleared | 2/27/2026 | TONY CHIANG |
| Sewer availability | Cleared | 2/27/2026 | TONY CHIANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Jad; Lic. No.: C96371 | 1149 S BROADWAY 6TH FLOOR LOS ANGELES, CA 90015 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/24/2026 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2026 | No Access for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 4/8/2026 | No Access for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2026 | No Access for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2026 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/12/2026 | Approved | KEVIN SARGSYAN |
| Insulation | 5/15/2026 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/18/2026 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 5/18/2026 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/22/2026 | Approved | KEVIN SARGSYAN |
| Insulation | 5/22/2026 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 5/27/2026 | Approved | KEVIN SARGSYAN |
| Final | 6/1/2026 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 6/1/2026 | SGSOV Not Ready | CARLOS MATAMOROS |
| Final | 6/4/2026 | OK to Issue CofO | KEVIN SARGSYAN |
| Green Building Final | 6/4/2026 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 6/4/2026 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 6/4/2026 | Approved | KEVIN SARGSYAN |