1135 N RAVOLI DR 90272

Certificate Information: 1135 N RAVOLI DR 90272

Application / Permit
26014-10000-00579
Plan Check / Job No.
B26LA05839
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Remodel and addition to (E) Single Family Dwelling w/ attached garage
Permit Issued
Issued on 3/4/2026
Issuing Office
Current Status
CofO in Progress on 6/4/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/17/2026 APPLICANT
Assigned to Plan Check Engineer 2/20/2026 AMY GUEVARRA
Corrections Issued 2/23/2026 AMY GUEVARRA
Plan Check Approved 3/4/2026 AMY GUEVARRA
Issued 3/4/2026 APPLICANT
CofO in Progress 6/4/2026 KEVIN SARGSYAN

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/26/2026 LANNY MERRICK
Eng Process Fee Ord 176,300 Cleared 2/27/2026 TONY CHIANG
Roof/Waste drainage to street Cleared 2/27/2026 TONY CHIANG
Sewer availability Cleared 2/27/2026 TONY CHIANG

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Jad; Lic. No.: C96371 1149 S BROADWAY   6TH FLOOR    LOS ANGELES, CA 90015

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/24/2026 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/7/2026 No Access for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 4/8/2026 No Access for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/8/2026 No Access for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/15/2026 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 5/12/2026 Approved KEVIN SARGSYAN
Insulation 5/15/2026 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 5/18/2026 Corrections Issued KEVIN SARGSYAN
Green Building Rough 5/18/2026 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 5/22/2026 Approved KEVIN SARGSYAN
Insulation 5/22/2026 Approved KEVIN SARGSYAN
Drywall Nailing 5/27/2026 Approved KEVIN SARGSYAN
Final 6/1/2026 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 6/1/2026 SGSOV Not Ready CARLOS MATAMOROS
Final 6/4/2026 OK to Issue CofO KEVIN SARGSYAN
Green Building Final 6/4/2026 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 6/4/2026 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 6/4/2026 Approved KEVIN SARGSYAN