13208 W JONESBORO PL 90049

Certificate Information: 13208 W JONESBORO PL 90049

Application / Permit
26014-10000-00384
Plan Check / Job No.
B25LA55742
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: SFD Addition of total 142 SF.
Permit Issued
Issued on 3/12/2026
Issuing Office
Current Status
CofO Issued on 7/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2026 APPLICANT
Assigned to Plan Check Engineer 2/10/2026 ZAW HAN
Corrections Issued 2/10/2026 ZAW HAN
Applicant returned to address corrections 3/6/2026 ALEC MOUSAKHANIAN
Plan Check Approved 3/12/2026 ZAW HAN
Issued 3/12/2026 APPLICANT
CofO in Progress 7/17/2026 HERBERT GIRON
Permit Finaled 7/20/2026 RICHARD STEINBACH
CofO Issued 7/20/2026 RICHARD STEINBACH
Permit Finaled 7/20/2026 RICHARD STEINBACH

Permit Application Clearance Information

CPC Cleared 2/17/2026 ALEX VELA
CPC Cleared 2/17/2026 ALEX VELA
Grading Pre-Inspection Cleared 2/19/2026 RUSSELL BONVOULOIR
Roof/Waste drainage to street Cleared 2/28/2026 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/10/2026 LEE GUILBEAUX
Sewer availability Cleared 3/10/2026 LEE GUILBEAUX

Contact Information

Contractor Globus Builder Inc; Lic. No.: 961380-B       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/10/2026 Approved HERBERT GIRON
PLUMBING-Rough 4/10/2026 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 4/20/2026 Partial Approval HERBERT GIRON
PLUMBING-Rough 4/20/2026 Partial Approval HERBERT GIRON
Deputy Wood Construction 4/22/2026 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/23/2026 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 4/30/2026 Corrections Issued HERBERT GIRON
PLUMBING-Rough 4/30/2026 Approved HERBERT GIRON
BUILDING-Rough-Frame 5/6/2026 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 5/6/2026 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/6/2026 Partial Approval HERBERT GIRON
Green Building Rough 5/6/2026 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 5/6/2026 Approved HERBERT GIRON
BUILDING-Rough-Frame 5/8/2026 Partial Approval HERBERT GIRON
Insulation 5/8/2026 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 5/8/2026 Partial Approval HERBERT GIRON
Shower Pan 5/8/2026 Approved HERBERT GIRON
BUILDING-Rough-Frame 5/13/2026 Partial Approval HERBERT GIRON
Drywall Nailing 5/13/2026 Partial Approval HERBERT GIRON
Insulation 5/13/2026 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 5/13/2026 Approved HERBERT GIRON
BUILDING-Rough-Frame 5/18/2026 Approved HERBERT GIRON
Drywall Nailing 5/18/2026 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/18/2026 Approved HERBERT GIRON
Green Building Rough 5/18/2026 Approved HERBERT GIRON
Insulation 5/18/2026 Approved HERBERT GIRON
ELECTRICAL-Final 7/14/2026 Corrections Issued HERBERT GIRON
HVAC-Final 7/14/2026 Approved HERBERT GIRON
PLUMBING-Final 7/14/2026 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 7/14/2026 SGSOV Approved HERBERT GIRON
Smoke Detectors 7/14/2026 Approved HERBERT GIRON
ELECTRICAL-Final 7/17/2026 Approved HERBERT GIRON
Final 7/17/2026 OK to Issue CofO HERBERT GIRON
Green Building Final 7/17/2026 Approved HERBERT GIRON