11401 W CLOVER AVE 90066

Certificate Information: 11401 W CLOVER AVE 90066

Application / Permit
26014-10000-00376
Plan Check / Job No.
B26LA03889
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR ALTERATION/REMODEL AND ADDITION TO AN EXISTING SINGLE FAMILY DWELLING.
Permit Issued
Issued on 4/29/2026
Issuing Office
Metro
Current Status
Issued on 4/29/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/2/2026 APPLICANT
Assigned to Plan Check Engineer 2/5/2026 ARMEN JIVALAGIAN
Assigned to Zoning Architect 2/5/2026 ELAHE MERRIKHI
Corrections Issued 2/10/2026 ARMEN JIVALAGIAN
Quality Review Completed 2/12/2026 PETER KIM
Building Plans Picked Up 2/23/2026 APPLICANT
Applicant returned to address corrections 4/16/2026 ARMEN JIVALAGIAN
Plan Check Approved 4/23/2026 ARMEN JIVALAGIAN
Issued 4/29/2026 APPLICANT

Permit Application Clearance Information

Low Impact Development (LID) Cleared 2/13/2026 SARAH YOUSSEF
Specific Plan Cleared 2/26/2026 HAMID GHAEMMAGHAMI
Eng Process Fee Ord 176,300 Cleared 3/6/2026 JESUS CISNEROS
Roof/Waste drainage to street Cleared 3/6/2026 JESUS CISNEROS
Sewer availability Cleared 3/6/2026 JESUS CISNEROS
Zoning Plan Check Cleared 4/3/2026 ELAHE MERRIKHI
GPI Written Notices Cleared 4/16/2026 ARMEN JIVALAGIAN
Grading Pre-Inspection Cleared 4/16/2026 ARMEN JIVALAGIAN

Contact Information

Architect Rezvani,, Farbod; Lic. No.: C32315 8537 PICKFORD ST      LOS ANGELES, CA 90035
Contractor Di Nalli Consulting Llc; Lic. No.: 942979-B 8537 PICKFORD STREET      LOS ANGELES, CA 90035
Engineer Askarian,, Soroosh; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Floor/Roof Diaphrgm/Shear Wall 6/8/2026   

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/18/2026 Conditional Approval KIRK SANDERS
Footing/Foundation/Slab 5/18/2026 Conditional Approval KIRK SANDERS
Underground Mechanical 5/18/2026 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 5/21/2026 Approved KIRK SANDERS