14728 W MCCORMICK ST 91411
Certificate Information: 14728 W MCCORMICK ST 91411
- Application / Permit
- 26014-10000-00243
- Plan Check / Job No.
- B26LA02351
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- [ePlan] Major Str. remodel to (E) SFD with new attached Garage - Bldg Sprinklered thru-out
- Permit Issued
- Issued on 4/28/2026
- Issuing Office
- Current Status
- Issued on 4/28/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/22/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2026 | MAHNAZ NOURHASHEMI |
| Assigned to Zoning Architect | 1/30/2026 | ALIZA NAZIR |
| Corrections Issued | 2/3/2026 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 2/13/2026 | GARO TELMI |
| Applicant returned to address corrections | 4/8/2026 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 4/17/2026 | MAHNAZ NOURHASHEMI |
| Issued | 4/28/2026 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 2/12/2026 | JACQUELINE TORRES |
| Sewer availability | Cleared | 2/19/2026 | ROSE STEIN-WENDT |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2026 | ROSE STEIN-WENDT |
| Roof/Waste drainage to street | Cleared | 2/23/2026 | ROSE STEIN-WENDT |
| Zoning Plan Check | Cleared | 3/18/2026 | ALIZA NAZIR |
| Trees in Parkway | Cleared | 3/20/2026 | BRANDON WONG |
| Permit | Cleared | 3/23/2026 | ROSE STEIN-WENDT |
Contact Information
| Contractor | Modern Works Inc; Lic. No.: 1060919-B | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/15/2026 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 5/15/2026 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 5/15/2026 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 5/20/2026 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 5/20/2026 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/2/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2026 | Partial Approval | MISAEL ESPARZA |